415 total Reset
The LFDC NEPA Tracker monitors active NEPA projects across National Forests in Washington, Oregon, California, and Alaska, giving advocates real-time visibility into proposed logging, land management, and restoration activities on public lands.

Projects are updated daily and organized to quickly find new projects and ones currently inviting public participation.

This database contains only the projects that have been published by USFS and that are/were recently in the NEPA analysis page.
Recent policy changes at USFS and the increased use of Categorical Exclusions have drastically reduced the share of USFS projects that get published and/or invite public comment. This means many projects can only be discovered by the public through field monitoring, long after the project has been planned, approved, and contracted.
If your local forests are not yet being tracked, submit feedback using the link above to request the expanded coverage.

There is no 'alert' feature at this time, so check back regularly to learn about new projects and opportunity to comment.
Clear all
Show only: Significant Effect Mixed Impact Restorative Impact Uncategorized
Show only: Newly Added Taking Comments Now Show Inactive Projects
*Impact level assigned automatically, based on keywords and is intended as a general guide only
38 of 415
Significant Effect
Significant Effect
Taking Comments Now! 6/29/26 11:59 PM PDT
Umatilla National Forest
Battle Bruin Integrated Vegetation Management Project
This project proposes to restore a healthy, diverse, and resilient forest ecosystem and create defensible fuel breaks for use during wildfire emergencies through the use of mechanical and non-mechanical thinning and fuels treatments, reforestation, and seeding and planting of native plants.
Learn About Wildfire Learn About Thinning
MilestoneDate
NEPA Start Date 4/2/2026
Finding/Decision Date
📍 North Fork John Day Ranger District 🏷 Vegetation management (other than forest products) Added: 2026-05-28
2 Days Left to Comment
Taking Comments Now! 6/29/26 11:59 PM PDT
Developing Proposal
MilestoneDate
NEPA Start Date 4/2/2026
Finding/Decision Date
Mixed Impact
Mixed Impact
MBS, Okan-Wen, Colville, Wallowa-Whitman, Fremont-Winema, Deschutes, Umatilla, Malheur
Region 6 Elite Tree Protection Project
The Pacific Northwest Region is collaborating with nine Forests to develop a region-wide project to protect whitebark pine trees (Pinus albicaulis) that have a high level of white pine blister rust resistance.
Learn About Wildfire Learn About Thinning
MilestoneDate
Scoping Start 04/2023 (Estimated)
Decision 09/2023 (Estimated)
Implementation 09/2023 (Estimated)
📍 R6 - Pacific Northwest Region All Units 🏷 Wildlife, fish, rare plants · Vegetation management (other than forest products) Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
Scoping Start 04/2023 (Estimated)
Decision 09/2023 (Estimated)
Implementation 09/2023 (Estimated)
Significant Effect
Significant Effect
Umatilla National Forest
54 North Fuels Reduction and Huckleberry Restoration Project
To restore resilience in dry upland forests by protecting old trees, reducing surface fuels, reducing overall forest density, and shifting composition from intolerant to fire tolerant species. Improve habitat for huckleberry.
Learn About Wildfire Learn About Thinning
MilestoneDate
NEPA Start Date 2/27/2026
Finding/Decision Date
📍 North Fork John Day Ranger District 🏷 Fuels management · Heritage resource management · Vegetation management (other than forest products) Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date 2/27/2026
Finding/Decision Date
Significant Effect
Significant Effect
Umatilla National Forest
Blue Mountains Forest Plan Revision
Land Management Plan revision for the Malheur, Umatilla, and Wallowa-Whitman National Forests, which will provide management direction on approximately 4.9 million acres of public lands. https://www.fs.usda.gov/r06/umatilla/planning/blue-mountains-forest-plan-revision
MilestoneDate
NEPA Start Date 8/5/2025
Finding/Decision Date
📍 Umatilla National Forest 🏷 Land management planning Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date 8/5/2025
Finding/Decision Date
Significant Effect
Significant Effect
Umatilla National Forest
Bone Point Planting CE
In accordance with the National Forest Management Act of 1976, this project proposes to replant trees in areas burned by the 2024 Bone Point Fire, where stocking levels have fallen below Umatilla National Forest Plan requirements.
Learn About Wildfire Learn About Thinning
📍 North Fork John Day Ranger District 🏷 Vegetation management (other than forest products) Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Umatilla National Forest
Double Snag Planting CE
The proposed action is to plant ponderosa pine, Douglas-fir, western larch, and western white pine seedlings by hand on 107 acres of the Double Snag fire burn scar. This will be non-RHCA planting.
Learn About Wildfire Learn About Thinning
Acres of The Double Snag Fire Burn Scar 107
📍 North Fork John Day Ranger District 🏷 Vegetation management (other than forest products) Added: 2026-05-28
Completed
Acres of The Double Snag Fire Burn Scar 107
Significant Effect
Significant Effect
Umatilla National Forest
Ellis Integrated Vegetation Project
The Ellis Project is being developed to improve wildlife habitat, restore resiliency against insect/disease and wildfire, protect values at risk, provide timber products, and enhance public and traditional land uses.
Learn About Wildfire Learn About Thinning
📍 North Fork John Day Ranger District 🏷 Forest products · Fuels management Added: 2026-05-28
Completed
Mixed Impact
Mixed Impact
Umatilla National Forest
FSR 47 Chipseal
There is a need to complete repairs initiated after the 2020 flood and resurfacing the existing 8 miles of asphalt pavement to provide a smooth-running surface for the portion of NFSR 47 that accesses the Forest Service land.
📍 Umatilla National Forest All Units 🏷 Road management Added: 2026-05-28
Completed
Restorative Impact
Restorative Impact
Umatilla National Forest
Forestwide Aquatic Restoration
Aquatic restoration on public and private lands within the boundary of the UNF and/or adjacent lands in boundary-spanning 5th HUC watersheds where restoration activities would benefit or help achieve Forest Service aquatic restoration goals.
📍 Umatilla National Forest All Units 🏷 Watershed management · Wildlife, fish, rare plants Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Umatilla National Forest
Lane Creek Drilling Survey
Proponent requesting to drill 5 holes 8" in diameter to depths of 15-50 feet to survey the location of bedrock to best determine stream channel design for culvert upgrade at Lane Creek and Highway 244.
📍 North Fork John Day Ranger District 🏷 Special use management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Umatilla National Forest
Lone Rock Post Fire Recovery CE
Address hazardous fuel conditions and insect outbreaks caused by the 2024 Lone Rock fire by creating a fuel break and reducing excess fuel loads. Regenerate areas of forest cover where viable seed sources of desired tree species are insufficient.
Learn About Wildfire Learn About Thinning
📍 Heppner Ranger District 🏷 Fuels management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Umatilla National Forest
Mottet Vegetation Management Project
Vegetation management project for stand structure and composition, socioeconomics by providing timber products.
Learn About Wildfire Learn About Thinning
MilestoneDate
NEPA Start Date 2/16/2026
Finding/Decision Date
📍 Walla Walla Ranger District 🏷 Vegetation management (other than forest products) Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date 2/16/2026
Finding/Decision Date
Uncategorized
Uncategorized
Umatilla National Forest
Mt. Misery Snowshelter Relocation
Mt. Misery Snowshelter proposed to be moved to reduce ongoing impacts and comply with NHPA.
MilestoneDate
NEPA Start Date 4/27/2026
Finding/Decision Date
📍 Pomeroy Ranger District Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date 4/27/2026
Finding/Decision Date
Uncategorized
Uncategorized
Umatilla National Forest
Pearson Tract Lot 1A Expansion (SUP)
Increase footprint from 562 sq. ft. by adding an additional 16%u2019x16%u2019 to the back side (southwest side) of the cabin bringing the total footprint of the cabin to 818 sq. ft., well below the 1,200 sq. ft. maximum.
📍 North Fork John Day Ranger District 🏷 Special use management Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Umatilla National Forest
Penland Lake Water Tank
Install 2000 gallon holding tank and 425 feet of waterline attached to private well to gravity feed 3 private cabins adjacent to FS Lands.
📍 Umatilla National Forest All Units 🏷 Special use management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Umatilla National Forest
Summit Road Fuels Reduction
The project would reduce fuels and improve forest health along the strategic control features of Forest Roads 31 (Summit Road) and 32 (Dry Creek).
Learn About Wildfire Learn About Thinning
📍 Walla Walla Ranger District 🏷 Vegetation management (other than forest products) · Fuels management Added: 2026-05-28
Completed
Mixed Impact
Mixed Impact
Umatilla National Forest
Tiger-Mill
The Tiger-Mill Project is being proposed to protect the Mill Creek Municipal Watershed and restore ecosystem processes and functions that foster landscape diversity and achieve desired vegetation conditions.
Learn About Wildfire Learn About Thinning
📍 Walla Walla Ranger District 🏷 Vegetation management (other than forest products) · Fuels management · Watershed management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Umatilla National Forest
Top Road Fuel Break (CE)
Top Road Fuelbreak Project is located in the Lower Big Wall Creek and Cupper Canyon-North Fork John Day River watersheds. The constructed fuelbreak will run along roadways and existing fire break on National Forest Service lands.
Learn About Wildfire Learn About Thinning
📍 Umatilla National Forest All Units 🏷 Fuels management Added: 2026-05-28
Completed
Restorative Impact
Restorative Impact
Umatilla National Forest
Tucannon Watershed Restoration Projects
Activities are planned to correct areas compromised by 2020 flood event, 2022 post-Green Ridge fire event and identified restoration needs. Activities include bank stabilization, culvert and road repair under the Forestwide Aquatics EA (47428).
MilestoneDate
Scoping Start 04/2024 (Estimated)
Decision 01/1970 (Estimated)
Implementation 07/2025 (Estimated)
📍 Umatilla National Forest All Units 🏷 Watershed management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
Scoping Start 04/2024 (Estimated)
Decision 01/1970 (Estimated)
Implementation 07/2025 (Estimated)
Significant Effect
Significant Effect
Umatilla National Forest
Zulu Post Fire Rehabilitation CE
This project will regenerate forest stands in burned areas that no longer have viable seed source for desired tree species. Treatments may include removing vegetation and planting seedlings in prepared areas.
Learn About Wildfire Learn About Thinning
📍 Heppner Ranger District 🏷 Fuels management Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Inyo National Forest
Airport Pit Disposal Site Permit Renewal
Reissuance of special use permit to the Town of Mammoth Lakes for operation of clean waste disposal at the Airport Pit
MilestoneDate
Scoping Start 01/2022 (Estimated)
Decision 03/2022 (Estimated)
Implementation 04/2022 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
On Hold Categorical Exclusion
MilestoneDate
Scoping Start 01/2022 (Estimated)
Decision 03/2022 (Estimated)
Implementation 04/2022 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
Control Silver Peak Project
Southern California Edison is proposing to update and reconfigure approximately 61 linear miles of two existing 55 kilovolt subtransmission lines originally designed and built in the 1930s. BLM is lead agency. Full description: https://bit.ly/44zSlg
MilestoneDate
NOI in Federal Register 12/29/2023
DEIS NOA in Federal Register 05/2025 (Estimated)
FEIS NOA in Federal Register 02/2026 (Estimated)
Objection Period Start 11/2025 (Estimated)
Decision 02/2026 (Estimated)
Implementation 04/2026 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
On Hold
MilestoneDate
NOI in Federal Register 12/29/2023
DEIS NOA in Federal Register 05/2025 (Estimated)
FEIS NOA in Federal Register 02/2026 (Estimated)
Objection Period Start 11/2025 (Estimated)
Decision 02/2026 (Estimated)
Implementation 04/2026 (Estimated)
Mixed Impact
Mixed Impact
Inyo National Forest
Coyote Flat OHV Recreation Enhancement
Improve road and motorized trail management in the Coyote Flat area. Repair system roads for safety and resource protection, review travel management decision in this area and adjust if needed for resource protection and recreation enhancement.
📍 Inyo National Forest All Units 🏷 Recreation management · Road management Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Inyo National Forest
Crystal Crag Water Storage Tank Replacement
The removal of two existing water storage tanks & constructing a new one. The new steel water storage tank will be 20,000-gallons, 16-foot diameter and 16 ft high. Including new inlet, outlet, drain, overflow, water supply, and distribution pipelines
MilestoneDate
Scoping Start 09/2024 (Estimated)
Decision 09/2024 (Estimated)
Implementation 09/2024 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
Scoping Start 09/2024 (Estimated)
Decision 09/2024 (Estimated)
Implementation 09/2024 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
E. Clampus Vitus Bodie Chapter No. 64 Tamarack Lodge Plaque
Bodie Chapter No. 64 of E. Clampus Vitus is to construct a historical marker w/ bronze plaque northeast of the Tamarack Lodge entrance commemorating the history of the Lodge & its contribution to the history of Mono County and the Mammoth Lakes Basin
MilestoneDate
Scoping Start 07/23/2024
Decision 08/2024 (Estimated)
Implementation 09/2024 (Estimated)
📍 Mammoth Ranger District 🏷 Heritage resource management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 07/23/2024
Decision 08/2024 (Estimated)
Implementation 09/2024 (Estimated)
Mixed Impact
Mixed Impact
Inyo National Forest
Eastern Sierra Climate and Communities Resilience Project
Project collaboration website link: https://www.eswildfirealliance.org/esccrp. Approx. 58,000 acre forest restoration project around the Town of Mammoth Lakes. Activities may include thinning of live and dead trees, pile burning, mechanical and hand.
Learn About Wildfire Learn About Thinning
Acres (approx.) 58,000
📍 Inyo National Forest All Units 🏷 Fuels management · Climate change adaptation Added: 2026-05-28
Completed
Acres (approx.) 58,000
Uncategorized
Uncategorized
Inyo National Forest
Inyo National Forest Over-Snow Vehicle (OSV) Use Designation
The Inyo National Forest is evaluating its management of over snow vehicle (OSV) use. The purpose of this project is to designate system roads, trails and areas where OSV use will be allowed, in compliance with 36 CFR 212, Subpart C.
MilestoneDate
Scoping Start 12/2026 (Estimated)
Comment Period 05/2027 (Estimated)
Objection Period Start 09/2027 (Estimated)
Decision 01/2028 (Estimated)
Implementation 02/2028 (Estimated)
📍 Inyo National Forest All Units 🏷 Recreation management Added: 2026-05-28
On Hold
MilestoneDate
Scoping Start 12/2026 (Estimated)
Comment Period 05/2027 (Estimated)
Objection Period Start 09/2027 (Estimated)
Decision 01/2028 (Estimated)
Implementation 02/2028 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
LADWP Long Valley Pole Removal and Pole Replacement Project
LADWP Utility Maintenance Project:1)removal of poles & replacement of poles in one line and 2)removal of poles & rehab in second line, 3)relinquish poles
MilestoneDate
Scoping Start 04/2024 (Estimated)
Decision 07/2024 (Estimated)
Implementation 10/2024 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
Scoping Start 04/2024 (Estimated)
Decision 07/2024 (Estimated)
Implementation 10/2024 (Estimated)
Significant Effect
Significant Effect
Inyo National Forest
Long Valley Exploration Drilling
On November 12, 2025, the Mammoth Lakes Ranger District of the Inyo National Forest received a Plan of Operations (Plan) from KORE USA Ltd. (KORE) for their Long Valley Exploration Drilling project in Mono County, California. KORE plans to conduct exploration-level activities for deposits of gold.
MilestoneDate
NEPA Start Date 4/3/2026
Finding/Decision Date
📍 Inyo National Forest 🏷 Minerals and geology Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date 4/3/2026
Finding/Decision Date
Uncategorized
Uncategorized
Inyo National Forest
Mammoth Mountain Main Lodge Redevelopment
Mammoth Mountain proposes redeveloping its Main Lodge area on private land, with related development on adjacent National Forest lands. Joint CEQA/NEPA analysis. Proposed construction/reconstruction of parking lots,buildings,chairlifts and ski runs.
MilestoneDate
NOI in Federal Register 11/14/2022
DEIS NOA in Federal Register 08/2025 (Estimated)
FEIS NOA in Federal Register 04/2025 (Estimated)
Objection Period Start 01/2026 (Estimated)
Decision 04/2026 (Estimated)
Implementation 04/2027 (Estimated)
📍 Inyo National Forest All Units 🏷 Recreation management · Special use management Added: 2026-05-28
In Progress
MilestoneDate
NOI in Federal Register 11/14/2022
DEIS NOA in Federal Register 08/2025 (Estimated)
FEIS NOA in Federal Register 04/2025 (Estimated)
Objection Period Start 01/2026 (Estimated)
Decision 04/2026 (Estimated)
Implementation 04/2027 (Estimated)
Significant Effect
Significant Effect
Inyo National Forest
Mazourka Canyon Abandoned Mine Lands Safety Closures
Safety closures and restoration for three abandoned mine sites in Mazourka Canyon. Closures will include plugging or placing bat-friendly gates on mine shafts, removing abandoned equipment or materials, and placing rocks for more natural appearance.
MilestoneDate
Scoping Start 07/17/2023
Decision 08/2025 (Estimated)
Implementation 09/2025 (Estimated)
📍 Inyo National Forest All Units 🏷 Minerals and geology Added: 2026-05-28
On Hold Categorical Exclusion
MilestoneDate
Scoping Start 07/17/2023
Decision 08/2025 (Estimated)
Implementation 09/2025 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
Permit Reissuances - Ongoing, various permit types
Ongoing and continuous reissuance of various special use authorizations. Examples of these are resorts, research activities, utilities and events. For further information on any specific permit or permitted activities, contact Erin Noesser.
MilestoneDate
Scoping Start 12/10/2018
Decision 06/2026 (Estimated)
Implementation 06/2026 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 12/10/2018
Decision 06/2026 (Estimated)
Implementation 06/2026 (Estimated)
Restorative Impact
Restorative Impact
Inyo National Forest
Reds Meadow Valley Recreation Site Renovations
Renovations & ecological restoration at 7 recreation sites / campgrounds in Reds Meadow Valley designed to enhance overall visitor experience, ensure recreation assets support current & future visitation & protect/restore ecologically sensitive areas
MilestoneDate
Scoping Start 05/08/2024
Decision 12/2024 (Estimated)
Implementation 06/2025 (Estimated)
📍 Mammoth Ranger District 🏷 Recreation management · Watershed management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 05/08/2024
Decision 12/2024 (Estimated)
Implementation 06/2025 (Estimated)
Restorative Impact
Restorative Impact
Inyo National Forest
Removal of Wild Horses Outside the Montgomery Pass Wild Horse Territory (MPWHT)
Gather and removal of excess wild horses that are located outside MPWHT to protect rangeland resources and proposed critical habitat for greater sage-grouse as well as address public safety concerns along highways/roadways.
📍 Mono Ranger District 🏷 Special area management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Inyo National Forest
Rock Creek Lodge Resort Wildfire Resilience
Fuels reduction and forest resilience project surrounding the Rock Creek Lakes Resort permit area on the Inyo National Forest. Project is funded by a National Resources Conservation Service grant.
Learn About Wildfire Learn About Thinning
MilestoneDate
Scoping Start 09/01/2024
Decision 03/2025 (Estimated)
Implementation 06/2025 (Estimated)
📍 Inyo National Forest All Units 🏷 Fuels management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 09/01/2024
Decision 03/2025 (Estimated)
Implementation 06/2025 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
Sherwin Area Recreation Plan 3 (SHARP)
Development of designated trails for protection of natural and cultural resources. This proposed action includes decommissioning of user created trails, reconstruction of user created trails, and new trail construction.
MilestoneDate
Scoping Start 04/2025 (Estimated)
Decision 06/2025 (Estimated)
Implementation 07/2025 (Estimated)
📍 Mammoth Ranger District 🏷 Recreation management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
Scoping Start 04/2025 (Estimated)
Decision 06/2025 (Estimated)
Implementation 07/2025 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
Southern California Edison Control-Silver Peak 55kV Reliability Project
Installation of remote fault indicators, packet routers, and installation of remote switches along with poles replacements.
MilestoneDate
NOI in Federal Register 11/2023 (Estimated)
DEIS NOA in Federal Register 03/2024 (Estimated)
FEIS NOA in Federal Register 06/2026 (Estimated)
Objection Period Start 06/2025 (Estimated)
Decision 06/2026 (Estimated)
Implementation 07/2026 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
On Hold
MilestoneDate
NOI in Federal Register 11/2023 (Estimated)
DEIS NOA in Federal Register 03/2024 (Estimated)
FEIS NOA in Federal Register 06/2026 (Estimated)
Objection Period Start 06/2025 (Estimated)
Decision 06/2026 (Estimated)
Implementation 07/2026 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
Vista Towers, multi-carrier facility at Little Antelope Communication Site
Placement of multi-carrier building and tower at the Little Antelope Communications Site
MilestoneDate
Scoping Start 05/2018 (Estimated)
Decision 08/2018 (Estimated)
Implementation 09/2018 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
On Hold Categorical Exclusion
MilestoneDate
Scoping Start 05/2018 (Estimated)
Decision 08/2018 (Estimated)
Implementation 09/2018 (Estimated)