415 total Reset
The LFDC NEPA Tracker monitors active NEPA projects across National Forests in Washington, Oregon, California, and Alaska, giving advocates real-time visibility into proposed logging, land management, and restoration activities on public lands.

Projects are updated daily and organized to quickly find new projects and ones currently inviting public participation.

This database contains only the projects that have been published by USFS and that are/were recently in the NEPA analysis page.
Recent policy changes at USFS and the increased use of Categorical Exclusions have drastically reduced the share of USFS projects that get published and/or invite public comment. This means many projects can only be discovered by the public through field monitoring, long after the project has been planned, approved, and contracted.
If your local forests are not yet being tracked, submit feedback using the link above to request the expanded coverage.

There is no 'alert' feature at this time, so check back regularly to learn about new projects and opportunity to comment.
Clear all
Show only: Significant Effect Mixed Impact Restorative Impact Uncategorized
Show only: Newly Added Taking Comments Now Show Inactive Projects
*Impact level assigned automatically, based on keywords and is intended as a general guide only
80 of 415
Significant Effect
Significant Effect
Mt. Hood National Forest
MTH Blowdown Insect and Disease Management
Remove excess buildup of dead and down trees including incidental removal of standing stressed dying trees from areas along National Forest System roads 46, 4640, and 5710 to control insect infestation and spread.
Learn About Wildfire Learn About Thinning
📍 Clackamas River Ranger District 🏷 Forest products · Fuels management · Vegetation management (other than forest products) Added: 2026-06-26
Completed
Significant Effect
Significant Effect
Mt. Hood National Forest
MTH Long Prairie Allotment - Reevaluation of Environmental Documents
The Long Prairie Allotment Decision Notice was signed in 2005. A Reevaluation of Environmental Documents (7 CFR 1b.9 (r)) was conducted to evaluate grazing on the Long Prairie Pasture within the allotment.
📍 Hood River Ranger District 🏷 Grazing management Added: 2026-06-24
Completed
Uncategorized
Uncategorized
Tongass National Forest
R10 TNF SRD 2026 Harbor Mountain USGS Landslide Monitoring Equipment
Monitoring equipment includes a fiberglass electronics enclosure, mounted rain gauge, a Temp/RH sensor and three instrumented soil profiles. The monitoring equipment functions year-round with occasional maintenance. The USGS is requesting authorization to have the equipment on site for 10 years.
📍 Sitka Ranger District 🏷 Special use management Added: 2026-06-16
Completed
Significant Effect
Significant Effect
Mt. Hood National Forest
South Wasco Ecosystem Resiliency
The project proposes to conduct commercial and non-commercial fuels and vegetation treatments on approximately 19,000 acres.
Learn About Wildfire Learn About Thinning
Acres (approx.) 19,000
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Mt. Hood National Forest 🏷 Forest products · Fuels management · Regulations, directives, orders · Vegetation management (other than forest products) Added: 2026-06-15
Developing Proposal
Acres (approx.) 19,000
MilestoneDate
NEPA Start Date
Finding/Decision Date
Significant Effect
Significant Effect
Mt. Hood National Forest
Basin Thinning Project
The purpose of this project is to restore forest health and resiliency on 110 acres of selected plantations.
Learn About Wildfire Learn About Thinning
Acres of Selected Plantations 110
📍 Zigzag Ranger District 🏷 Forest products · Vegetation management (other than forest products) Added: 2026-05-28
Completed
Acres of Selected Plantations 110
Uncategorized
Uncategorized
Mt. Hood National Forest
Big Eddy-Ostrander Conductor Replacement Project
For more information the Big Eddy-Ostrander Conductor Replacement Project, visit the BPA project website https://www.bpa.gov/learn-and-participate/public-involvement-decisions/project-reviews/big-eddy-ostrander-project
📍 Mt. Hood National Forest All Units 🏷 Special use management Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Mt. Hood National Forest
Cascade Utilities Reflector Decommissioning
A communication reflector, owned by Cascade Utilities, is no longer is use and needs to be removed from National Forest System lands. The microwave dish is 20 feet by 24 feet in size and weighs 9,170 pounds. Once removed, the site would be restored.
📍 Clackamas River Ranger District 🏷 Special use management · Projects that may affect wilderness (for mailing list contacts) Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Mt. Hood National Forest
Cloud Cap Inn Water System Renovation
The proposed action is reconstruction of the existing spring box, redevelopment of the existing spring, and installation of a new distribution main from the spring box to the Cloud Cap Saddle Campground, Cloud Cap Inn and Snowshoe Cabin.
📍 Hood River Ranger District 🏷 Facility management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Mt. Hood National Forest
Consent for Geothermal Leasing
The Bureau of Land Management (BLM) received nominations of National Forest System lands to be considered for a future, competitive geothermal lease sale. The Forest Service is considering whether to consent to the BLM to lease these lands.
📍 Clackamas River Ranger District 🏷 Minerals and geology Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Mt. Hood National Forest
Hootnanny Insect and Disease
The primary purposes of this project are to reduce the risk of landscape level disturbance and increase forest resiliency to insect and disease.
Learn About Wildfire Learn About Thinning
📍 Barlow Ranger District 🏷 Forest products · Vegetation management (other than forest products) · Fuels management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Mt. Hood National Forest
MTH Anvil Vegetation Management Project
This project seeks to improve forest health and diversity in plantations. In addition, this project seeks to reduce excessive fuel loading primarily along forest roads. Approximately 4,000 acres may be proposed for vegetation and fuels treatments.
Learn About Wildfire Learn About Thinning
Acres (approx.) 4,000
MilestoneDate
NEPA Start Date 2/3/2026
Finding/Decision Date
📍 Clackamas River Ranger District 🏷 Forest products · Fuels management · Vegetation management (other than forest products) Added: 2026-05-28
Developing Proposal
Acres (approx.) 4,000
MilestoneDate
NEPA Start Date 2/3/2026
Finding/Decision Date
Uncategorized
Uncategorized
Mt. Hood National Forest
MTH Cascade Utilities Fiber Optic at Ripplebrook
Install fiber communication cable along existing roads, to provide high speed internet to the Ripplebrook administrative site.
📍 Mt. Hood National Forest 🏷 Special use management Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Mt. Hood National Forest
MTH Clear Branch Dam Remediation
There is a need to remediate Clear Branch Dam to meet current dam safety and environmental compliance standards in order to continue to provide a clean dependable water supply for the Upper Hood River valley. More information at: clearbranchdam.com.
MilestoneDate
NEPA Start Date 6/18/2025
Finding/Decision Date
📍 Mt. Hood National Forest 🏷 Special use management Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date 6/18/2025
Finding/Decision Date
Significant Effect
Significant Effect
Mt. Hood National Forest
MTH Lost Lake Late Successional Reserve Acre Swap
There is a need to amend the Forest Plan to remove the high use recreational area of Lost Lake Resort, Campground and Day Use Area from Late-successional Reserve (LSR), and reallocate more appropriate areas as LSR.
MilestoneDate
NEPA Start Date 8/20/2025
Finding/Decision Date
📍 Mt. Hood National Forest 🏷 Land management planning Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date 8/20/2025
Finding/Decision Date
Uncategorized
Uncategorized
Mt. Hood National Forest
MTH Timberline Chairlifts and Improvements
To improve connectivity between Summit Pass and Timberline Lodge, enhance skiing experience, and improve communications, the following is proposed: replacement of Summit Pass chairlift and new chairlift construction, ski terrain improvements, and fiber optic cable installation.
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Mt. Hood National Forest 🏷 Special use management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date
Finding/Decision Date
Uncategorized
Uncategorized
Mt. Hood National Forest
Portland General Electric (PGE) Undergrounding Summit 13 Distribution Powerline
As part of PGE's Wildfire Mitigation Plan, there is a need to minimize wildland fire risk associated with utilities in the National Forest. Therefore, this project would underground approximately 5 miles of existing powerline.
📍 Zigzag Ranger District 🏷 Special use management Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Mt. Hood National Forest
Routine Repair and Maintenance of Existing Utilities in Ski Areas
Ski areas have ongoing repair and maintenance needs to meet Forest Service standards. This project allows for ski areas to better maintain existing utilities within permitted areas.
📍 Mt. Hood National Forest All Units 🏷 Special use management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Mt. Hood National Forest
Stone Creek Vegetation Management Project
The project seeks to improve forest health and diversity on approximately 3,225 acres within the Oak Grove Fork Clackamas River watershed.
Learn About Wildfire Learn About Thinning
Acres (approx.) 3,225
📍 Clackamas River Ranger District 🏷 Forest products · Vegetation management (other than forest products) · Fuels management · Road management Added: 2026-05-28
Completed
Acres (approx.) 3,225
Uncategorized
Uncategorized
Mt. Hood National Forest
Timberline Mountain Bike Connector Trails
There is a need to move advanced riders away from beginner riders more efficiently by adding short trail connectors from the Gravy Train Trail and upper Brobi Wan Trail. Also, a 245-foot trail alignment would be added to The Rock Trail.
📍 Zigzag Ranger District 🏷 Recreation management · Special use management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Mt. Hood National Forest
Wapinitia Fuels Reduction
The purpose of this project is to improve forest conditions by reducing accumulated fuels on approximately 100 acres west of the Wapinitia subdivision. Work includes non-commercial hand-cutting trees 6-8 inches DBH. Access will use existing roads.
Learn About Wildfire Learn About Thinning
Acres (approx.) 100
📍 Zigzag Ranger District 🏷 Vegetation management (other than forest products) · Fuels management Added: 2026-05-28
Completed
Acres (approx.) 100
Uncategorized
Uncategorized
Inyo National Forest
Airport Pit Disposal Site Permit Renewal
Reissuance of special use permit to the Town of Mammoth Lakes for operation of clean waste disposal at the Airport Pit
MilestoneDate
Scoping Start 01/2022 (Estimated)
Decision 03/2022 (Estimated)
Implementation 04/2022 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
On Hold Categorical Exclusion
MilestoneDate
Scoping Start 01/2022 (Estimated)
Decision 03/2022 (Estimated)
Implementation 04/2022 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
Control Silver Peak Project
Southern California Edison is proposing to update and reconfigure approximately 61 linear miles of two existing 55 kilovolt subtransmission lines originally designed and built in the 1930s. BLM is lead agency. Full description: https://bit.ly/44zSlg
MilestoneDate
NOI in Federal Register 12/29/2023
DEIS NOA in Federal Register 05/2025 (Estimated)
FEIS NOA in Federal Register 02/2026 (Estimated)
Objection Period Start 11/2025 (Estimated)
Decision 02/2026 (Estimated)
Implementation 04/2026 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
On Hold
MilestoneDate
NOI in Federal Register 12/29/2023
DEIS NOA in Federal Register 05/2025 (Estimated)
FEIS NOA in Federal Register 02/2026 (Estimated)
Objection Period Start 11/2025 (Estimated)
Decision 02/2026 (Estimated)
Implementation 04/2026 (Estimated)
Mixed Impact
Mixed Impact
Inyo National Forest
Coyote Flat OHV Recreation Enhancement
Improve road and motorized trail management in the Coyote Flat area. Repair system roads for safety and resource protection, review travel management decision in this area and adjust if needed for resource protection and recreation enhancement.
📍 Inyo National Forest All Units 🏷 Recreation management · Road management Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Inyo National Forest
Crystal Crag Water Storage Tank Replacement
The removal of two existing water storage tanks & constructing a new one. The new steel water storage tank will be 20,000-gallons, 16-foot diameter and 16 ft high. Including new inlet, outlet, drain, overflow, water supply, and distribution pipelines
MilestoneDate
Scoping Start 09/2024 (Estimated)
Decision 09/2024 (Estimated)
Implementation 09/2024 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
Scoping Start 09/2024 (Estimated)
Decision 09/2024 (Estimated)
Implementation 09/2024 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
E. Clampus Vitus Bodie Chapter No. 64 Tamarack Lodge Plaque
Bodie Chapter No. 64 of E. Clampus Vitus is to construct a historical marker w/ bronze plaque northeast of the Tamarack Lodge entrance commemorating the history of the Lodge & its contribution to the history of Mono County and the Mammoth Lakes Basin
MilestoneDate
Scoping Start 07/23/2024
Decision 08/2024 (Estimated)
Implementation 09/2024 (Estimated)
📍 Mammoth Ranger District 🏷 Heritage resource management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 07/23/2024
Decision 08/2024 (Estimated)
Implementation 09/2024 (Estimated)
Mixed Impact
Mixed Impact
Inyo National Forest
Eastern Sierra Climate and Communities Resilience Project
Project collaboration website link: https://www.eswildfirealliance.org/esccrp. Approx. 58,000 acre forest restoration project around the Town of Mammoth Lakes. Activities may include thinning of live and dead trees, pile burning, mechanical and hand.
Learn About Wildfire Learn About Thinning
Acres (approx.) 58,000
📍 Inyo National Forest All Units 🏷 Fuels management · Climate change adaptation Added: 2026-05-28
Completed
Acres (approx.) 58,000
Uncategorized
Uncategorized
Inyo National Forest
Inyo National Forest Over-Snow Vehicle (OSV) Use Designation
The Inyo National Forest is evaluating its management of over snow vehicle (OSV) use. The purpose of this project is to designate system roads, trails and areas where OSV use will be allowed, in compliance with 36 CFR 212, Subpart C.
MilestoneDate
Scoping Start 12/2026 (Estimated)
Comment Period 05/2027 (Estimated)
Objection Period Start 09/2027 (Estimated)
Decision 01/2028 (Estimated)
Implementation 02/2028 (Estimated)
📍 Inyo National Forest All Units 🏷 Recreation management Added: 2026-05-28
On Hold
MilestoneDate
Scoping Start 12/2026 (Estimated)
Comment Period 05/2027 (Estimated)
Objection Period Start 09/2027 (Estimated)
Decision 01/2028 (Estimated)
Implementation 02/2028 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
LADWP Long Valley Pole Removal and Pole Replacement Project
LADWP Utility Maintenance Project:1)removal of poles & replacement of poles in one line and 2)removal of poles & rehab in second line, 3)relinquish poles
MilestoneDate
Scoping Start 04/2024 (Estimated)
Decision 07/2024 (Estimated)
Implementation 10/2024 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
Scoping Start 04/2024 (Estimated)
Decision 07/2024 (Estimated)
Implementation 10/2024 (Estimated)
Significant Effect
Significant Effect
Inyo National Forest
Long Valley Exploration Drilling
On November 12, 2025, the Mammoth Lakes Ranger District of the Inyo National Forest received a Plan of Operations (Plan) from KORE USA Ltd. (KORE) for their Long Valley Exploration Drilling project in Mono County, California. KORE plans to conduct exploration-level activities for deposits of gold.
MilestoneDate
NEPA Start Date 4/3/2026
Finding/Decision Date
📍 Inyo National Forest 🏷 Minerals and geology Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date 4/3/2026
Finding/Decision Date
Uncategorized
Uncategorized
Inyo National Forest
Mammoth Mountain Main Lodge Redevelopment
Mammoth Mountain proposes redeveloping its Main Lodge area on private land, with related development on adjacent National Forest lands. Joint CEQA/NEPA analysis. Proposed construction/reconstruction of parking lots,buildings,chairlifts and ski runs.
MilestoneDate
NOI in Federal Register 11/14/2022
DEIS NOA in Federal Register 08/2025 (Estimated)
FEIS NOA in Federal Register 04/2025 (Estimated)
Objection Period Start 01/2026 (Estimated)
Decision 04/2026 (Estimated)
Implementation 04/2027 (Estimated)
📍 Inyo National Forest All Units 🏷 Recreation management · Special use management Added: 2026-05-28
In Progress
MilestoneDate
NOI in Federal Register 11/14/2022
DEIS NOA in Federal Register 08/2025 (Estimated)
FEIS NOA in Federal Register 04/2025 (Estimated)
Objection Period Start 01/2026 (Estimated)
Decision 04/2026 (Estimated)
Implementation 04/2027 (Estimated)
Significant Effect
Significant Effect
Inyo National Forest
Mazourka Canyon Abandoned Mine Lands Safety Closures
Safety closures and restoration for three abandoned mine sites in Mazourka Canyon. Closures will include plugging or placing bat-friendly gates on mine shafts, removing abandoned equipment or materials, and placing rocks for more natural appearance.
MilestoneDate
Scoping Start 07/17/2023
Decision 08/2025 (Estimated)
Implementation 09/2025 (Estimated)
📍 Inyo National Forest All Units 🏷 Minerals and geology Added: 2026-05-28
On Hold Categorical Exclusion
MilestoneDate
Scoping Start 07/17/2023
Decision 08/2025 (Estimated)
Implementation 09/2025 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
Permit Reissuances - Ongoing, various permit types
Ongoing and continuous reissuance of various special use authorizations. Examples of these are resorts, research activities, utilities and events. For further information on any specific permit or permitted activities, contact Erin Noesser.
MilestoneDate
Scoping Start 12/10/2018
Decision 06/2026 (Estimated)
Implementation 06/2026 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 12/10/2018
Decision 06/2026 (Estimated)
Implementation 06/2026 (Estimated)
Restorative Impact
Restorative Impact
Inyo National Forest
Reds Meadow Valley Recreation Site Renovations
Renovations & ecological restoration at 7 recreation sites / campgrounds in Reds Meadow Valley designed to enhance overall visitor experience, ensure recreation assets support current & future visitation & protect/restore ecologically sensitive areas
MilestoneDate
Scoping Start 05/08/2024
Decision 12/2024 (Estimated)
Implementation 06/2025 (Estimated)
📍 Mammoth Ranger District 🏷 Recreation management · Watershed management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 05/08/2024
Decision 12/2024 (Estimated)
Implementation 06/2025 (Estimated)
Restorative Impact
Restorative Impact
Inyo National Forest
Removal of Wild Horses Outside the Montgomery Pass Wild Horse Territory (MPWHT)
Gather and removal of excess wild horses that are located outside MPWHT to protect rangeland resources and proposed critical habitat for greater sage-grouse as well as address public safety concerns along highways/roadways.
📍 Mono Ranger District 🏷 Special area management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Inyo National Forest
Rock Creek Lodge Resort Wildfire Resilience
Fuels reduction and forest resilience project surrounding the Rock Creek Lakes Resort permit area on the Inyo National Forest. Project is funded by a National Resources Conservation Service grant.
Learn About Wildfire Learn About Thinning
MilestoneDate
Scoping Start 09/01/2024
Decision 03/2025 (Estimated)
Implementation 06/2025 (Estimated)
📍 Inyo National Forest All Units 🏷 Fuels management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 09/01/2024
Decision 03/2025 (Estimated)
Implementation 06/2025 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
Sherwin Area Recreation Plan 3 (SHARP)
Development of designated trails for protection of natural and cultural resources. This proposed action includes decommissioning of user created trails, reconstruction of user created trails, and new trail construction.
MilestoneDate
Scoping Start 04/2025 (Estimated)
Decision 06/2025 (Estimated)
Implementation 07/2025 (Estimated)
📍 Mammoth Ranger District 🏷 Recreation management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
Scoping Start 04/2025 (Estimated)
Decision 06/2025 (Estimated)
Implementation 07/2025 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
Southern California Edison Control-Silver Peak 55kV Reliability Project
Installation of remote fault indicators, packet routers, and installation of remote switches along with poles replacements.
MilestoneDate
NOI in Federal Register 11/2023 (Estimated)
DEIS NOA in Federal Register 03/2024 (Estimated)
FEIS NOA in Federal Register 06/2026 (Estimated)
Objection Period Start 06/2025 (Estimated)
Decision 06/2026 (Estimated)
Implementation 07/2026 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
On Hold
MilestoneDate
NOI in Federal Register 11/2023 (Estimated)
DEIS NOA in Federal Register 03/2024 (Estimated)
FEIS NOA in Federal Register 06/2026 (Estimated)
Objection Period Start 06/2025 (Estimated)
Decision 06/2026 (Estimated)
Implementation 07/2026 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
Vista Towers, multi-carrier facility at Little Antelope Communication Site
Placement of multi-carrier building and tower at the Little Antelope Communications Site
MilestoneDate
Scoping Start 05/2018 (Estimated)
Decision 08/2018 (Estimated)
Implementation 09/2018 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
On Hold Categorical Exclusion
MilestoneDate
Scoping Start 05/2018 (Estimated)
Decision 08/2018 (Estimated)
Implementation 09/2018 (Estimated)
Uncategorized
Uncategorized
Tongass National Forest
Amalga Trail Reconstruction - Sections 3 through 6
Improve Amalga Trail from mile 1.45 to mile 5.56, known as sections 3 to 6. Other improvements include improving signage, and establishing several rest areas along the trail.
📍 Juneau Ranger District 🏷 Recreation management Added: 2026-05-28
Completed
Restorative Impact
Restorative Impact
Tongass National Forest
Bad Day Creek Restoration
Remove culverts and replace with new structures at 2 sites, add large wood to stream channel and remove aggregate fill from the floodplain. Hand crews would complete most of the work, but heavy equipment and blasting may be needed to remove culverts.
📍 Yakutat Ranger District 🏷 Wildlife, fish, rare plants · Watershed management Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Tongass National Forest
Breiland Slough Cabin Replacement
Proposal to replace the existing Breiland Slough public use recreation cabin and improve access to the site.
MilestoneDate
Scoping Start 09/21/2021
Decision 01/2024 (Estimated)
Implementation 02/2024 (Estimated)
📍 Petersburg Ranger District 🏷 Recreation management Added: 2026-05-28
Cancelled Categorical Exclusion
MilestoneDate
Scoping Start 09/21/2021
Decision 01/2024 (Estimated)
Implementation 02/2024 (Estimated)
Uncategorized
Uncategorized
Tongass National Forest
Cannon Beach Cabin Construction
Proposal to convert a developed campsite within the Yakutat Beach Recreation Area into a public use recreation cabin site.
📍 Yakutat Ranger District 🏷 Recreation management Added: 2026-05-28
Completed
Mixed Impact
Mixed Impact
Tongass National Forest
Cannon Beach Parking Expansion
Expand existing parking lot, add new parking areas, and construct about 750 feet of new road to improve traffic flow and user safety, and meet capacity demands at the Cannon Beach Recreation Site.
📍 Yakutat Ranger District 🏷 Recreation management · Road management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Tongass National Forest
Chichagof Old-Growth Blowdown Salvage Sale
Proposed salvage timber sale within in a blow down area adjacent to NFS road 8530. The harvest area would include 3 units and provide approximately 88 thousand board feet of timber from about 25 acres.
Learn About Thinning
Thousand Board Feet 88
Acres (approx.) 25
📍 Hoonah Ranger District 🏷 Forest products Added: 2026-05-28
Completed
Thousand Board Feet 88
Acres (approx.) 25
Significant Effect
Significant Effect
Tongass National Forest
Continuation of Zarembo Minerals Plan of Operations 2023 to 2024
Proposal to continue authorizing exploration activities by Zarembo Minerals Co. on Zarembo Island until July 2023. Activities to continue include surface exploration and drilling, use of a closed spur road, and onsite storage of drilling equipment.
MilestoneDate
Scoping Start 04/06/2022
Decision 09/2023 (Estimated)
Implementation 09/2023 (Estimated)
📍 Wrangell Ranger District 🏷 Minerals and geology Added: 2026-05-28
Cancelled Categorical Exclusion
MilestoneDate
Scoping Start 04/06/2022
Decision 09/2023 (Estimated)
Implementation 09/2023 (Estimated)
Restorative Impact
Restorative Impact
Tongass National Forest
Cube Cove Restoration
Following the purchase of 22,890 acres, the District proposes to restore and preserve wilderness character in the Cube Cove portion of the Kootznoowoo Wilderness through re-establishing hydrologic function.
Acres 22,890
📍 Admiralty Island National Monument 🏷 Watershed management · Wildlife, fish, rare plants · Projects that may affect wilderness (for mailing list contacts) Added: 2026-05-28
Completed
Acres 22,890
Uncategorized
Uncategorized
Tongass National Forest
False Bay Cabin New Construction
Construct a new recreation cabin at False Bay, on Chichagof Island, approximately 25 miles from Hoonah Alaska on FS Road 8530. Proposed features include: cabin, vault toilet, woodshed, picnic table/fire ring, parking area, access trails and buoy.
📍 Hoonah Ranger District 🏷 Recreation management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Tongass National Forest
Greens Creek North Extension Project
Hecla Greens Creek Mining Company proposes to extend the existing dry-stack tailings disposal facility and incorporate waste rock co-disposal techniques in a northward direction for additional tailings and waste rock storage capacity.
📍 Admiralty Island National Monument 🏷 Minerals and geology Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Tongass National Forest
Hecla Greens Creek Mining Company Surface Exploration 2026-2030
Hecla Greens Creek Mining Company proposes to extend their surface exploration authorization by five years and incorporate new areas of interest.
📍 Admiralty Island National Monument 🏷 Minerals and geology Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Tongass National Forest
Helicopter Pad Reconstruction
Replace and improve three helicopter pads at the existing Etolin, Farragut, and Fools radio repeater administrative sites.
📍 Wrangell Ranger District 🏷 Facility management Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Tongass National Forest
Herbert Glacier Cabin
Construct a new recreation cabin accessible to the public by helicopter or by foot via a 4.4-mile hike on the Herbert Glacier Trail. Other infrastructure includes a vault-style outhouse, a gathering area, a helicopter landing site and access trails.
📍 Juneau Ranger District 🏷 Recreation management Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Tongass National Forest
Herbert River - Installation of Environmental Monitoring Equipment
Installation and maintenance of 1 stream gauge and 2 meteorological stations to gather environmental data in support of the New Amalga Gold Mine.
📍 Juneau Ranger District 🏷 Special use management Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Tongass National Forest
Juneau Ranger District Office to Bunkhouse Telecom Cable Connection
Install an underground Forest Service-owned and operated fiber optic cable between the district office building and Bunkhouse A, and between Bunkhouses A and B.
📍 Juneau Ranger District 🏷 Facility management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Tongass National Forest
Kake Redcedar Transplant
Annually, for the next 5 yrs, extract 200 to 300 native western redcedar seedlings growing on the roadbed of National Forest System road 6041. Plant along the Kake road system in areas disturbed by management activities. Only handtools would be used.
📍 Petersburg Ranger District 🏷 Vegetation management (other than forest products) Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Tongass National Forest
Maybeso Potable Water System Replacement
Replace the potable water system for several Forest Service administrative buildings and a small school. Includes improvement of water reservoir, channel spillway and filtration treatment system.
📍 Craig Ranger District 🏷 Facility management · Research Added: 2026-05-28
Completed
Restorative Impact
Restorative Impact
Tongass National Forest
Mendenhall Glacier Visitor Facility Improvements
Constructing facility improvements within the Mendenhall Glacier Recreation Area to accommodate anticipated visitor growth.
📍 Juneau Ranger District 🏷 Recreation management · Special area management · Facility management Added: 2026-05-28
Completed
Mixed Impact
Mixed Impact
Tongass National Forest
Nemo Road Stabilization
Approximately 5 miles of FS Road 6265 (Nemo-Skip Loop Road) & associated culverts will be repaired. Current wood waste road base will be replaced with more stable gravel surface, as well as other activities associated with road stabilization.
📍 Wrangell Ranger District 🏷 Road management Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Tongass National Forest
Pats Lake Shelters
Construct a group shelter and three-sided shelter at existing roadside day use sites adjacent to Pats Lake. Both sites would include a vault toilet and parking area.
📍 Wrangell Ranger District 🏷 Recreation management Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Tongass National Forest
Pats Lake Trail Extension
Construct 1/2 mile of trail to connect existing Pats Creek Trail to National Forest System road 6259. Construction includes aggregate, concrete steps and elevated boardwalk. Up to three spur trails proposed leading to wildlife viewing platforms.
📍 Wrangell Ranger District 🏷 Recreation management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Tongass National Forest
R10 TNF ANM Hecla Greens Creek Mine Treated Wastewater Outfall Line 002A 2026
Hecla Greens Creek Mining Co. proposes to install 14-inch dia. 1474-foot long treated water outfall pipeline, within their existing, permitted 30' wide ROW on NFS lands.
📍 Admiralty National Monument 🏷 Minerals and geology · Special use management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Tongass National Forest
R10 TNF HRD 2025 Chichagof Small Sales
To make 70 acres available for community access to small-scale timber sales utilizing ground-based logging systems without the use of heavy machinery to harvest. Multiple small sales provide for opportunities for harvest of firewood, sawlogs and other timber products for commercial use.
Learn About Thinning
Acres 70
MilestoneDate
NEPA Start Date 8/29/2025
Finding/Decision Date
📍 Hoonah Ranger District 🏷 Forest products Added: 2026-05-28
Developing Proposal Categorical Exclusion
Acres 70
MilestoneDate
NEPA Start Date 8/29/2025
Finding/Decision Date
Significant Effect
Significant Effect
Tongass National Forest
R10 TNF HRD Millrock Exploration Corp - Apex El Nido Project
The activity for the Apex-El Nido Exploration project entails conducting hard rock exploration through diamond core drilling. It is anticipated a maximum of 15 holes will be drilled.
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Hoonah Ranger District 🏷 Minerals and geology Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date
Finding/Decision Date
Uncategorized
Uncategorized
Tongass National Forest
R10 TNF JRD 2026 Bonnie Brae Trail Rehabilitation
Bonnie Brae Trail Rehabilitation project will rehabilitate and harden an existing trail mostly within the existing trail prism, except where minor reroutes or switchbacks are needed. This trail connects the Bonnie Brae area to Treadwell Ditch Trail.
📍 Juneau Ranger District 🏷 Recreation management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Tongass National Forest
R10 TNF JRD Glacial outburst flood barrier along Backloop Road 2026
Due to the increasing annual glacial outburst flood event, the City and Borough of Juneau proposes emergency flood barrier construction of either HESCO barriers or a berm/levee parallel to the north of Backloop Road extending approximately 1,500 feet east of the bridge on state ROW and NFS lands.
📍 Juneau Ranger District 🏷 Land management planning Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Tongass National Forest
R10 TNF KMRD 2026 Deer Mountain Trail Maintenance
Project will complete trail maintenance and repairs on the Deer Mountain Trail from the trailhead to the first overlook, a distance of approximately one mile. Trail maintenance may include brushing and logging out the trail, and cleaning culverts and drainage ditches.
📍 Ketchikan - Misty Ranger District 🏷 Recreation management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Tongass National Forest
R10 TNF KMRD South Revillagigedo Integrated Resource Project
The Forest Service is proposing a multi-year project involving a variety of timber harvest, road construction, watershed restoration and recreation activities.
Learn About Thinning
MilestoneDate
NEPA Start Date 8/8/2018
Finding/Decision Date
📍 Ketchikan - Misty Ranger District 🏷 Forest products · Recreation management · Road management · Wildlife, fish, rare plants Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date 8/8/2018
Finding/Decision Date
Uncategorized
Uncategorized
Tongass National Forest
R10 TNF SRD 2026 Remote Admin Camp Improvements
Improvements at the existing False Island and Corner Bay administrative sites.
📍 Sitka Ranger District 🏷 Facility management Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Tongass National Forest
R10 TNF SRD Deer Lake Coho Rearing Facility Permit Re-Issuance (NSRAA)
Re-issue special use permit for coho rearing facility- run by NSRAA
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Sitka Ranger District Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date
Finding/Decision Date
Uncategorized
Uncategorized
Tongass National Forest
R10 TNF SRD Hidden Falls Fish Hatchery Alaska Department of Fish and Game
Re-Issue of special use permit for a salmon hatchery run by Northern Southeast Regional Aquaculture Association.
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Sitka Ranger District Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date
Finding/Decision Date
Uncategorized
Uncategorized
Tongass National Forest
R10 TNF TBRD 2026 North Thorne Bay State Access
This project includes construction of 1 new temporary road on Forest Service lands and reconstruction of 1 existing temporary road on Forest Service lands for easement access to State of Alaska planned timber sales. Anticipated timing is summer FY26 & FY27.
📍 Thorne Bay Ranger District 🏷 Special use management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Tongass National Forest
R10 TNF TBRD Twin Mountain II Timber Sale
The proposed action is expected to produce about 26.8 million board feet of timber from approximately 1,655 acres of National Forest System lands in the Staney and Red Bay areas within the Thorne Bay RD. Other activities include road construction, reconstruction, maintenance and decommissioning.
LFDC Commented Learn About Thinning
Acres (approx.) 1,655
Million Board Feet 26.8
MilestoneDate
NEPA Start Date 9/14/2020
Finding/Decision Date
📍 Thorne Bay Ranger District 🏷 Forest products · Road management Added: 2026-05-28
Developing Proposal
Acres (approx.) 1,655
Million Board Feet 26.8
MilestoneDate
NEPA Start Date 9/14/2020
Finding/Decision Date
Significant Effect
Significant Effect
Tongass National Forest
R10 TNF Tongass National Forest Land Management Plan Revision
Land management plan revision for the Tongass National Forest under the 2012 Planning Rule.
LFDC Commented
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Tongass National Forest 🏷 Land management planning Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date
Finding/Decision Date
Uncategorized
Uncategorized
Tongass National Forest
R10 TNF YRD 2026 Alsek River Special Use Facilities
Proposal to modify an existing permitted use within the authorized area, with minor additions and improvements to existing facilities.
📍 Tongass National Forest 🏷 Special use management Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Tongass National Forest
R10 TNF YRD 2026 Italio River Special Use Facilities
Proposal to modify an existing permitted use within the authorized area, with minor additions and improvements to existing facilities.
📍 Tongass National Forest 🏷 Special use management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Tongass National Forest
R10 TNF YRD 2026 Yakutat Community Needs
The overall objective of this project is to create a small-scale timber sale opportunity that benefits local operators and sawmills, while addressing ongoing environmental and safety issues. In addition to utilizing the naturally available salvage material, the project will facilitate access to the
Learn About Thinning
📍 Yakutat Ranger District 🏷 Forest products Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Tongass National Forest
Southside Helicopter Sale
The Thorne Bay Ranger District is proposing to harvest approximately 125 acres of old growth live trees due to interest received from a prospective purchaser located on Prince of Wales Island. The area is 10 miles south of Naukati.
Learn About Thinning
Acres of Old Growth 125
📍 Thorne Bay Ranger District 🏷 Forest products Added: 2026-05-28
Completed
Acres of Old Growth 125
Uncategorized
Uncategorized
Tongass National Forest
Taku Inlet Monitoring Equipment Special Use Permit
Request from the US Border Patrol for a 10-year special use permit to install and maintain cameras to monitor vessels entering and exiting the Taku Inlet.
📍 Juneau Ranger District 🏷 Special use management Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Tongass National Forest
Temporary Storage Sites for Neck Lake Road Reconstruction
Proposal to establish 5 temporary storage and stockpile sites on National Forest System land in support of the Neck Lake Rd reconstruction project. Site areas total about 3.25 acres. Materials and improvements would be removed upon permit expiration.
Acres (approx.) 3.25
📍 Thorne Bay Ranger District 🏷 Special use management Added: 2026-05-28
Completed
Acres (approx.) 3.25
Significant Effect
Significant Effect
Tongass National Forest
Thorne Bay Basin Integrated Resource Management Project
This project would improve wildlife habitat, provide commercial young-growth harvest opportunities, implement riparian and road restoration activities in the project areas, as well as to provide support for employment and economic growth.
Learn About Wildfire Learn About Thinning
📍 Thorne Bay Ranger District 🏷 Wildlife, fish, rare plants · Forest products · Vegetation management (other than forest products) · Watershed management · Road management · Climate change adaptation Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Tongass National Forest
Whale Pass Young Growth Small Sales
Harvest approximately 70 acres of live young-growth trees.
Learn About Thinning
Acres (approx.) 70
📍 Thorne Bay Ranger District 🏷 Forest products Added: 2026-05-28
Completed
Acres (approx.) 70