415 total Reset
The LFDC NEPA Tracker monitors active NEPA projects across National Forests in Washington, Oregon, California, and Alaska, giving advocates real-time visibility into proposed logging, land management, and restoration activities on public lands.

Projects are updated daily and organized to quickly find new projects and ones currently inviting public participation.

This database contains only the projects that have been published by USFS and that are/were recently in the NEPA analysis page.
Recent policy changes at USFS and the increased use of Categorical Exclusions have drastically reduced the share of USFS projects that get published and/or invite public comment. This means many projects can only be discovered by the public through field monitoring, long after the project has been planned, approved, and contracted.
If your local forests are not yet being tracked, submit feedback using the link above to request the expanded coverage.

There is no 'alert' feature at this time, so check back regularly to learn about new projects and opportunity to comment.
Clear all
Show only: Significant Effect Mixed Impact Restorative Impact Uncategorized
Show only: Newly Added Taking Comments Now Show Inactive Projects
*Impact level assigned automatically, based on keywords and is intended as a general guide only
41 of 415
Restorative Impact
Restorative Impact
Okanogan-Wenatchee National Forest
Frazer Creek BDA 2026
In Upper Frazer Creek on US Forest Service managed lands, the Methow Okanogan Beaver Project (MBP) proposes to support restoration of natural processes toward stream and floodplain connectivity, increased base streamflows, and climate resilience in the watershed.
MilestoneDate
NEPA Start Date 4/29/2026
Finding/Decision Date
📍 Methow Valley Ranger District 🏷 Special use management · Watershed management Added: 2026-06-24
In Progress Categorical Exclusion
MilestoneDate
NEPA Start Date 4/29/2026
Finding/Decision Date
Restorative Impact
Restorative Impact
MBS, ONF, Okan-Wen, Colville
Pacific Northwest National Scenic Trail Comprehensive Plan
The Comprehensive Plan will develop administrative and management objectives and practices and desired conditions for the Pacific Northwest National Scenic Trail on public lands in Forest Service Regions 1 and Regions 6.
📍 R6 - Pacific Northwest Region All Units 🏷 Recreation management · Special area management Added: 2026-05-28
Completed
Mixed Impact
Mixed Impact
MBS, Okan-Wen, Colville, Wallowa-Whitman, Fremont-Winema, Deschutes, Umatilla, Malheur
Region 6 Elite Tree Protection Project
The Pacific Northwest Region is collaborating with nine Forests to develop a region-wide project to protect whitebark pine trees (Pinus albicaulis) that have a high level of white pine blister rust resistance.
Learn About Wildfire Learn About Thinning
MilestoneDate
Scoping Start 04/2023 (Estimated)
Decision 09/2023 (Estimated)
Implementation 09/2023 (Estimated)
📍 R6 - Pacific Northwest Region All Units 🏷 Wildlife, fish, rare plants · Vegetation management (other than forest products) Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
Scoping Start 04/2023 (Estimated)
Decision 09/2023 (Estimated)
Implementation 09/2023 (Estimated)
Uncategorized
Uncategorized
Okanogan-Wenatchee National Forest
Canyon and Trout Creek Trail Bridge Replacements 2024
Replace damaged trail bridges at Jackita Ridge trail # 738 over Canyon Creek and W. Fork Methow trail #480 over Trout Creek.
MilestoneDate
Scoping Start 07/02/2024
Decision 09/2025 (Estimated)
Implementation 10/2025 (Estimated)
📍 Methow Valley Ranger District 🏷 Recreation management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 07/02/2024
Decision 09/2025 (Estimated)
Implementation 10/2025 (Estimated)
Uncategorized
Uncategorized
Okanogan-Wenatchee National Forest
Chelan PUD Fiber Optic Installation Project
The project proposes aerial fiber optic installation, use, operation, and maintenance along roads within the existing transmission line right-of-way.
MilestoneDate
Scoping Start 06/2025 (Estimated)
Decision 08/2025 (Estimated)
Implementation 05/2026 (Estimated)
📍 Wenatchee River Ranger District 🏷 Special use management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
Scoping Start 06/2025 (Estimated)
Decision 08/2025 (Estimated)
Implementation 05/2026 (Estimated)
Mixed Impact
Mixed Impact
Okanogan-Wenatchee National Forest
Chumstick to LP Project
Landscape scale terrestrial restoration project.
Learn About Wildfire Learn About Thinning
MilestoneDate
Scoping Start 09/25/2023
Comment Period 08/2025 (Estimated)
Decision 12/2025 (Estimated)
Implementation 01/2026 (Estimated)
📍 Wenatchee River Ranger District 🏷 Fuels management · Watershed management Added: 2026-05-28
On Hold
MilestoneDate
Scoping Start 09/25/2023
Comment Period 08/2025 (Estimated)
Decision 12/2025 (Estimated)
Implementation 01/2026 (Estimated)
Mixed Impact
Mixed Impact
Okanogan-Wenatchee National Forest
Cougar Creek Danger Trees
The Forest Service is proposing the removal of dead trees within 150 feet of selected roads. Any tree that is dead, and is within 150 feet of the road, will be subject to removal regardless of species.
Learn About Wildfire Learn About Thinning
📍 Entiat Ranger District 🏷 Road management · Fuels management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Okanogan-Wenatchee National Forest
Eagle Creek Project
Commercial, non-commercial, and fuels activities to reduce wildfire risk, improve timber sands and forest structure, and improve wildlife habitat.
Learn About Wildfire Learn About Thinning
📍 Wenatchee River Ranger District 🏷 Forest products · Fuels management · Wildlife, fish, rare plants Added: 2026-05-28
Completed
Mixed Impact
Mixed Impact
Okanogan-Wenatchee National Forest
Entiat River Road, North Fork Entiat Road, Duncan Road, Shady Pass Danger Tree Removal
Removal of dead trees within 150 feet of selected roads to address potential of dead trees falling on vehicles or people and blocking ingress/egress.
📍 Entiat Ranger District 🏷 Road management Added: 2026-05-28
Completed
Mixed Impact
Mixed Impact
Okanogan-Wenatchee National Forest
FSR6910 Road Repair and maintenance
Project is to issue a road use permit to T-Mobile to complete light maintenance road repairs to FSR6910 to the communications site on Round Mountain.
📍 Wenatchee River Ranger District 🏷 Road management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Okanogan-Wenatchee National Forest
Forest-wide Tree Seed Orchard Fire Protection Project
Maintain and protect developed tree seed orchards by thinning trees and maintaining fuel break in the surrounding 300 foot buffer.
Learn About Wildfire Learn About Thinning
MilestoneDate
Scoping Start 05/01/2023
Decision 01/1970 (Estimated)
Implementation 11/2023 (Estimated)
📍 Okanogan-Wenatchee National Forest All Units 🏷 Vegetation management (other than forest products) Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 05/01/2023
Decision 01/1970 (Estimated)
Implementation 11/2023 (Estimated)
Restorative Impact
Restorative Impact
Okanogan-Wenatchee National Forest
Gold Creek Valley Restoration
A multi-partner effort to recover Gold Creek bull trout populations by correcting habitat conditions which create significant mortality, reconnecting the creek and floodplain, and restoring natural processes. Provide recreation at this valued site.
📍 Cle Elum Ranger District 🏷 Wildlife, fish, rare plants Added: 2026-05-28
Completed
Mixed Impact
Mixed Impact
Okanogan-Wenatchee National Forest
Icicle Creek Rockfall Mitigation project
Provide rockfall mitigation on up to three slopes on Icicle Creek Road from MP4.3 to 4.8. Project is scheduled to be completed Fall of 2023.
MilestoneDate
Scoping Start 12/05/2022
Decision 01/1970 (Estimated)
Implementation 08/2023 (Estimated)
📍 Wenatchee River Ranger District 🏷 Road management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 12/05/2022
Decision 01/1970 (Estimated)
Implementation 08/2023 (Estimated)
Significant Effect
Significant Effect
Okanogan-Wenatchee National Forest
Lower Lake Cle Elum Fuel Break Project
Establish linear fuel breaks around lower Lake Cle Elum to reduce the risk of uncharacteristic wildfire, incorporating existing linear features.
Learn About Wildfire Learn About Thinning
📍 Cle Elum Ranger District 🏷 Fuels management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Okanogan-Wenatchee National Forest
Midnight Restoration
Landscape-scale wildfire risk reduction and terrestrial restoration project in Rader Creek, lower Wolf Creek, and upper Twisp River drainages. Excludes Lake Chelan-Sawtooth Wilderness.
Learn About Wildfire Learn About Thinning
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Methow Valley Ranger District 🏷 Forest products · Fuels management · Road management · Vegetation management (other than forest products) · Watershed management · Wildlife, fish, rare plants Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date
Finding/Decision Date
Restorative Impact
Restorative Impact
Okanogan-Wenatchee National Forest
Mineral Creek Road Decommissioning
This project would decommission approx. 1 mile of FS-4600 (Mineral Creek Road), which would no longer be needed after the Upper Kachess River Restoration project constructs a new trailhead for the Mineral Creek Trail.
MilestoneDate
Scoping Start 07/2025 (Estimated)
Comment Period 07/2025 (Estimated)
Objection Period Start 08/2025 (Estimated)
Decision 09/2025 (Estimated)
Implementation 09/2025 (Estimated)
📍 Cle Elum Ranger District 🏷 Wildlife, fish, rare plants Added: 2026-05-28
Developing Proposal
MilestoneDate
Scoping Start 07/2025 (Estimated)
Comment Period 07/2025 (Estimated)
Objection Period Start 08/2025 (Estimated)
Decision 09/2025 (Estimated)
Implementation 09/2025 (Estimated)
Mixed Impact
Mixed Impact
Okanogan-Wenatchee National Forest
Planning and Management of Domestic Sheep and Goat Grazing within the Range of Bighorn Sheep
Proposal to amend Land and Resource Management Plans to provide forest plan direction for managing domestic sheep and goat grazing within the range of Bighorn sheep to better provide for bighorn sheep viability in the context of range management.
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Okanogan-Wenatchee National Forest 🏷 Grazing management · Land management planning · Wildlife, fish, rare plants Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date
Finding/Decision Date
Restorative Impact
Restorative Impact
Okanogan-Wenatchee National Forest
Railroad Creek Driftwood Harbor Protection
Temporarily place 6-10 ecology blocks above OHW to deflect overbank flows from Railroad Creek away from a potential avulsion low spot that flows directly into Driftwood Harbor.
📍 Chelan Ranger District 🏷 Watershed management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Okanogan-Wenatchee National Forest
South Fork Tieton Prescribed Fire Project
Wildfire Crisis Strategy Project
Learn About Wildfire Learn About Thinning
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Naches Ranger District 🏷 Fuels management · Vegetation management (other than forest products) Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date
Finding/Decision Date
Significant Effect
Significant Effect
Okanogan-Wenatchee National Forest
Upper Methow
Landscape-scale wildfire risk reduction and terrestrial restoration project in Goat Creek, Cub Creek and Lost River drainages using emergency authorities.
Learn About Wildfire Learn About Thinning
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Methow Valley Ranger District 🏷 Forest products · Vegetation management (other than forest products) · Watershed management · Wildlife, fish, rare plants Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date
Finding/Decision Date
Significant Effect
Significant Effect
Okanogan-Wenatchee National Forest
Upper Swauk Restoration Project
Fuels & Forest Health EAD Project. Proposing forest restoration activities including commercial and non-commercial thinning, prescribed fire, fuels breaks, aquatic restoration activities, and transportation system changes.
Learn About Wildfire Learn About Thinning
Acres 36,567
MilestoneDate
NEPA Start Date 10/10/2023
Finding/Decision Date
📍 Cle Elum Ranger District 🏷 Forest products · Fuels management · Road management · Watershed management · Wildlife, fish, rare plants Added: 2026-05-28
Developing Proposal
Acres 36,567
MilestoneDate
NEPA Start Date 10/10/2023
Finding/Decision Date
Uncategorized
Uncategorized
Okanogan-Wenatchee National Forest
Wenatchee Mountain Alpine Huts Special Use Permit
Issue 2-year transitional priority use special use authorization for seasonal (winter) lodging facilities and outfitter guiding at DeRoux Campground, North Fork Teanaway River.
📍 Cle Elum Ranger District 🏷 Special use management Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Okanogan-Wenatchee National Forest
White Pass Ski Area - Chairlift 4 Replacement Project
White Pass proposes to replace the existing double chairlift with a new quad chairlift. The new lift would be installed in the same alignment as the current lift, with the same bottom and top terminal locations.
MilestoneDate
Scoping Start 01/08/2025
Decision 03/2025 (Estimated)
Implementation 06/2025 (Estimated)
📍 Naches Ranger District 🏷 Special use management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 01/08/2025
Decision 03/2025 (Estimated)
Implementation 06/2025 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
Airport Pit Disposal Site Permit Renewal
Reissuance of special use permit to the Town of Mammoth Lakes for operation of clean waste disposal at the Airport Pit
MilestoneDate
Scoping Start 01/2022 (Estimated)
Decision 03/2022 (Estimated)
Implementation 04/2022 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
On Hold Categorical Exclusion
MilestoneDate
Scoping Start 01/2022 (Estimated)
Decision 03/2022 (Estimated)
Implementation 04/2022 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
Control Silver Peak Project
Southern California Edison is proposing to update and reconfigure approximately 61 linear miles of two existing 55 kilovolt subtransmission lines originally designed and built in the 1930s. BLM is lead agency. Full description: https://bit.ly/44zSlg
MilestoneDate
NOI in Federal Register 12/29/2023
DEIS NOA in Federal Register 05/2025 (Estimated)
FEIS NOA in Federal Register 02/2026 (Estimated)
Objection Period Start 11/2025 (Estimated)
Decision 02/2026 (Estimated)
Implementation 04/2026 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
On Hold
MilestoneDate
NOI in Federal Register 12/29/2023
DEIS NOA in Federal Register 05/2025 (Estimated)
FEIS NOA in Federal Register 02/2026 (Estimated)
Objection Period Start 11/2025 (Estimated)
Decision 02/2026 (Estimated)
Implementation 04/2026 (Estimated)
Mixed Impact
Mixed Impact
Inyo National Forest
Coyote Flat OHV Recreation Enhancement
Improve road and motorized trail management in the Coyote Flat area. Repair system roads for safety and resource protection, review travel management decision in this area and adjust if needed for resource protection and recreation enhancement.
📍 Inyo National Forest All Units 🏷 Recreation management · Road management Added: 2026-05-28
Completed
Uncategorized
Uncategorized
Inyo National Forest
Crystal Crag Water Storage Tank Replacement
The removal of two existing water storage tanks & constructing a new one. The new steel water storage tank will be 20,000-gallons, 16-foot diameter and 16 ft high. Including new inlet, outlet, drain, overflow, water supply, and distribution pipelines
MilestoneDate
Scoping Start 09/2024 (Estimated)
Decision 09/2024 (Estimated)
Implementation 09/2024 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
Scoping Start 09/2024 (Estimated)
Decision 09/2024 (Estimated)
Implementation 09/2024 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
E. Clampus Vitus Bodie Chapter No. 64 Tamarack Lodge Plaque
Bodie Chapter No. 64 of E. Clampus Vitus is to construct a historical marker w/ bronze plaque northeast of the Tamarack Lodge entrance commemorating the history of the Lodge & its contribution to the history of Mono County and the Mammoth Lakes Basin
MilestoneDate
Scoping Start 07/23/2024
Decision 08/2024 (Estimated)
Implementation 09/2024 (Estimated)
📍 Mammoth Ranger District 🏷 Heritage resource management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 07/23/2024
Decision 08/2024 (Estimated)
Implementation 09/2024 (Estimated)
Mixed Impact
Mixed Impact
Inyo National Forest
Eastern Sierra Climate and Communities Resilience Project
Project collaboration website link: https://www.eswildfirealliance.org/esccrp. Approx. 58,000 acre forest restoration project around the Town of Mammoth Lakes. Activities may include thinning of live and dead trees, pile burning, mechanical and hand.
Learn About Wildfire Learn About Thinning
Acres (approx.) 58,000
📍 Inyo National Forest All Units 🏷 Fuels management · Climate change adaptation Added: 2026-05-28
Completed
Acres (approx.) 58,000
Uncategorized
Uncategorized
Inyo National Forest
Inyo National Forest Over-Snow Vehicle (OSV) Use Designation
The Inyo National Forest is evaluating its management of over snow vehicle (OSV) use. The purpose of this project is to designate system roads, trails and areas where OSV use will be allowed, in compliance with 36 CFR 212, Subpart C.
MilestoneDate
Scoping Start 12/2026 (Estimated)
Comment Period 05/2027 (Estimated)
Objection Period Start 09/2027 (Estimated)
Decision 01/2028 (Estimated)
Implementation 02/2028 (Estimated)
📍 Inyo National Forest All Units 🏷 Recreation management Added: 2026-05-28
On Hold
MilestoneDate
Scoping Start 12/2026 (Estimated)
Comment Period 05/2027 (Estimated)
Objection Period Start 09/2027 (Estimated)
Decision 01/2028 (Estimated)
Implementation 02/2028 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
LADWP Long Valley Pole Removal and Pole Replacement Project
LADWP Utility Maintenance Project:1)removal of poles & replacement of poles in one line and 2)removal of poles & rehab in second line, 3)relinquish poles
MilestoneDate
Scoping Start 04/2024 (Estimated)
Decision 07/2024 (Estimated)
Implementation 10/2024 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
Scoping Start 04/2024 (Estimated)
Decision 07/2024 (Estimated)
Implementation 10/2024 (Estimated)
Significant Effect
Significant Effect
Inyo National Forest
Long Valley Exploration Drilling
On November 12, 2025, the Mammoth Lakes Ranger District of the Inyo National Forest received a Plan of Operations (Plan) from KORE USA Ltd. (KORE) for their Long Valley Exploration Drilling project in Mono County, California. KORE plans to conduct exploration-level activities for deposits of gold.
MilestoneDate
NEPA Start Date 4/3/2026
Finding/Decision Date
📍 Inyo National Forest 🏷 Minerals and geology Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date 4/3/2026
Finding/Decision Date
Uncategorized
Uncategorized
Inyo National Forest
Mammoth Mountain Main Lodge Redevelopment
Mammoth Mountain proposes redeveloping its Main Lodge area on private land, with related development on adjacent National Forest lands. Joint CEQA/NEPA analysis. Proposed construction/reconstruction of parking lots,buildings,chairlifts and ski runs.
MilestoneDate
NOI in Federal Register 11/14/2022
DEIS NOA in Federal Register 08/2025 (Estimated)
FEIS NOA in Federal Register 04/2025 (Estimated)
Objection Period Start 01/2026 (Estimated)
Decision 04/2026 (Estimated)
Implementation 04/2027 (Estimated)
📍 Inyo National Forest All Units 🏷 Recreation management · Special use management Added: 2026-05-28
In Progress
MilestoneDate
NOI in Federal Register 11/14/2022
DEIS NOA in Federal Register 08/2025 (Estimated)
FEIS NOA in Federal Register 04/2025 (Estimated)
Objection Period Start 01/2026 (Estimated)
Decision 04/2026 (Estimated)
Implementation 04/2027 (Estimated)
Significant Effect
Significant Effect
Inyo National Forest
Mazourka Canyon Abandoned Mine Lands Safety Closures
Safety closures and restoration for three abandoned mine sites in Mazourka Canyon. Closures will include plugging or placing bat-friendly gates on mine shafts, removing abandoned equipment or materials, and placing rocks for more natural appearance.
MilestoneDate
Scoping Start 07/17/2023
Decision 08/2025 (Estimated)
Implementation 09/2025 (Estimated)
📍 Inyo National Forest All Units 🏷 Minerals and geology Added: 2026-05-28
On Hold Categorical Exclusion
MilestoneDate
Scoping Start 07/17/2023
Decision 08/2025 (Estimated)
Implementation 09/2025 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
Permit Reissuances - Ongoing, various permit types
Ongoing and continuous reissuance of various special use authorizations. Examples of these are resorts, research activities, utilities and events. For further information on any specific permit or permitted activities, contact Erin Noesser.
MilestoneDate
Scoping Start 12/10/2018
Decision 06/2026 (Estimated)
Implementation 06/2026 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 12/10/2018
Decision 06/2026 (Estimated)
Implementation 06/2026 (Estimated)
Restorative Impact
Restorative Impact
Inyo National Forest
Reds Meadow Valley Recreation Site Renovations
Renovations & ecological restoration at 7 recreation sites / campgrounds in Reds Meadow Valley designed to enhance overall visitor experience, ensure recreation assets support current & future visitation & protect/restore ecologically sensitive areas
MilestoneDate
Scoping Start 05/08/2024
Decision 12/2024 (Estimated)
Implementation 06/2025 (Estimated)
📍 Mammoth Ranger District 🏷 Recreation management · Watershed management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 05/08/2024
Decision 12/2024 (Estimated)
Implementation 06/2025 (Estimated)
Restorative Impact
Restorative Impact
Inyo National Forest
Removal of Wild Horses Outside the Montgomery Pass Wild Horse Territory (MPWHT)
Gather and removal of excess wild horses that are located outside MPWHT to protect rangeland resources and proposed critical habitat for greater sage-grouse as well as address public safety concerns along highways/roadways.
📍 Mono Ranger District 🏷 Special area management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Inyo National Forest
Rock Creek Lodge Resort Wildfire Resilience
Fuels reduction and forest resilience project surrounding the Rock Creek Lakes Resort permit area on the Inyo National Forest. Project is funded by a National Resources Conservation Service grant.
Learn About Wildfire Learn About Thinning
MilestoneDate
Scoping Start 09/01/2024
Decision 03/2025 (Estimated)
Implementation 06/2025 (Estimated)
📍 Inyo National Forest All Units 🏷 Fuels management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 09/01/2024
Decision 03/2025 (Estimated)
Implementation 06/2025 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
Sherwin Area Recreation Plan 3 (SHARP)
Development of designated trails for protection of natural and cultural resources. This proposed action includes decommissioning of user created trails, reconstruction of user created trails, and new trail construction.
MilestoneDate
Scoping Start 04/2025 (Estimated)
Decision 06/2025 (Estimated)
Implementation 07/2025 (Estimated)
📍 Mammoth Ranger District 🏷 Recreation management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
Scoping Start 04/2025 (Estimated)
Decision 06/2025 (Estimated)
Implementation 07/2025 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
Southern California Edison Control-Silver Peak 55kV Reliability Project
Installation of remote fault indicators, packet routers, and installation of remote switches along with poles replacements.
MilestoneDate
NOI in Federal Register 11/2023 (Estimated)
DEIS NOA in Federal Register 03/2024 (Estimated)
FEIS NOA in Federal Register 06/2026 (Estimated)
Objection Period Start 06/2025 (Estimated)
Decision 06/2026 (Estimated)
Implementation 07/2026 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
On Hold
MilestoneDate
NOI in Federal Register 11/2023 (Estimated)
DEIS NOA in Federal Register 03/2024 (Estimated)
FEIS NOA in Federal Register 06/2026 (Estimated)
Objection Period Start 06/2025 (Estimated)
Decision 06/2026 (Estimated)
Implementation 07/2026 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
Vista Towers, multi-carrier facility at Little Antelope Communication Site
Placement of multi-carrier building and tower at the Little Antelope Communications Site
MilestoneDate
Scoping Start 05/2018 (Estimated)
Decision 08/2018 (Estimated)
Implementation 09/2018 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
On Hold Categorical Exclusion
MilestoneDate
Scoping Start 05/2018 (Estimated)
Decision 08/2018 (Estimated)
Implementation 09/2018 (Estimated)