The LFDC NEPA Tracker monitors active NEPA projects across National Forests in Washington, Oregon, California, and Alaska, giving advocates real-time visibility into proposed logging, land management, and restoration activities on public lands.

Projects are updated daily and organized to quickly find new projects and ones currently inviting public participation.

This database contains only the projects that have been published by USFS and that are/were recently in the NEPA analysis page.
Recent policy changes at USFS and the increased use of Categorical Exclusions have drastically reduced the share of USFS projects that get published and/or invite public comment. This means many projects can only be discovered by the public through field monitoring, long after the project has been planned, approved, and contracted.
If your local forests are not yet being tracked, submit feedback using the link above to request the expanded coverage.

There is no 'alert' feature at this time, so check back regularly to learn about new projects and opportunity to comment.
Clear all
Show only: Significant Effect Mixed Impact Restorative Impact Uncategorized
Show only: Newly Added Taking Comments Now Show Inactive Projects
*Impact level assigned automatically, based on keywords and is intended as a general guide only
25 of 162 active projects
Mixed Impact
Mixed Impact
Taking Comments Now! 6/30/26 11:59 PM PDT
Los Padres National Forest
Wildfire Risk Reduction Project (formerly the Ecological Restoration Project) PALS # 62369
The project is designed to increase community/infrastructure protection, improve wildfire containment opportunities, and improve vegetation resilience to environmental stressors. A notice of Emergency Situation Determination approval has been posted. Comments will be accepted from June 24-30, 2026.
Learn About Wildfire Learn About Thinning
MilestoneDate
NEPA Start Date 7/29/2022
Finding/Decision Date
📍 Los Padres National Forest 🏷 Fuels management · Vegetation management (other than forest products) · Watershed management · Wildlife, fish, rare plants Added: 2026-05-28
3 Days Left to Comment
Taking Comments Now! 6/30/26 11:59 PM PDT
Developing Proposal
MilestoneDate
NEPA Start Date 7/29/2022
Finding/Decision Date
Significant Effect
Significant Effect
Mt. Hood National Forest
South Wasco Ecosystem Resiliency
The project proposes to conduct commercial and non-commercial fuels and vegetation treatments on approximately 19,000 acres.
Learn About Wildfire Learn About Thinning
Acres (approx.) 19,000
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Mt. Hood National Forest 🏷 Forest products · Fuels management · Regulations, directives, orders · Vegetation management (other than forest products) Added: 2026-06-15
Developing Proposal
Acres (approx.) 19,000
MilestoneDate
NEPA Start Date
Finding/Decision Date
Uncategorized
Uncategorized
Gifford Pinchot National Forest
Forest Wide Thinning & Potential Control Line Treatments
The proposed action would include 2 primary elements: plantation thinning of previously regenerated stands under 80 years of age, and small diameter hand thinning within 500 feet of roadsides identified by fire management staff as PCLs for use in future wildfire management.
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Gifford Pinchot National Forest Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date
Finding/Decision Date
Significant Effect
Significant Effect
Gifford Pinchot National Forest
Little White Salmon Forest Resiliency and Fire Risk Mitigation Project
Increase forest resiliency to climate-related stressors and mitigate fire risk to highly valued resources in the Little White Salmon Watershed. Proposed actions will include commercial timber harvest, fuels treatments and other restoration projects.
Learn About Wildfire Learn About Thinning
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Mt. Adams Ranger District 🏷 Vegetation management (other than forest products) Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date
Finding/Decision Date
Uncategorized
Uncategorized
Gifford Pinchot National Forest
Mount Adams South Climb / Cold Springs Trailhead Improvements
Trailhead improvements necessary to ensure quality visitor experiences, improved sanitation and safety, and resource protection and restoration in the vicinity of the Mt. Adams South Climb (#183) and Cold Springs (#72) trailheads.
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Mt. Adams Ranger District 🏷 Recreation management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date
Finding/Decision Date
Uncategorized
Uncategorized
Gifford Pinchot National Forest
Mount Margaret Backcountry Toilet Replacement
Project proposes to replace aging toilet facilities at 8 backcountry campsites in the Mount Margaret Backcountry Area within Mount St. Helens National Volcanic Monument.
MilestoneDate
NEPA Start Date 9/25/2025
Finding/Decision Date 5/26/2026
📍 Mount St. Helens National Volcanic Monument 🏷 Recreation management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
NEPA Start Date 9/25/2025
Finding/Decision Date 5/26/2026
Significant Effect
Significant Effect
Gifford Pinchot National Forest
Review of Wind River Consent to Geothermal Lease Request
The Gifford Pinchot National Forest is responding to two requests provided by Bureau of Land Management to evaluate consent to lease two nominated parcels of Forest Service lands for geothermal exploration and development.
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Gifford Pinchot National Forest 🏷 Minerals and geology Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date
Finding/Decision Date
Uncategorized
Uncategorized
Gifford Pinchot National Forest
Spirit Lake Outflow Safety Improvement Project
The Project proposes to evaluate options to improve safety of the outflow at Spirit Lake located within the Mount St. Helens National Volcanic Monument. A draft Record of Decision and corresponding documents will be published on July 7, 2026 opening up Objections for the Project.
MilestoneDate
NEPA Start Date 9/30/2024
Finding/Decision Date
📍 Gifford Pinchot National Forest 🏷 Regulations, directives, orders Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date 9/30/2024
Finding/Decision Date
Significant Effect
Significant Effect
Mt. Hood National Forest
MTH Anvil Vegetation Management Project
This project seeks to improve forest health and diversity in plantations. In addition, this project seeks to reduce excessive fuel loading primarily along forest roads. Approximately 4,000 acres may be proposed for vegetation and fuels treatments.
Learn About Wildfire Learn About Thinning
Acres (approx.) 4,000
MilestoneDate
NEPA Start Date 2/3/2026
Finding/Decision Date
📍 Clackamas River Ranger District 🏷 Forest products · Fuels management · Vegetation management (other than forest products) Added: 2026-05-28
Developing Proposal
Acres (approx.) 4,000
MilestoneDate
NEPA Start Date 2/3/2026
Finding/Decision Date
Uncategorized
Uncategorized
Mt. Hood National Forest
MTH Clear Branch Dam Remediation
There is a need to remediate Clear Branch Dam to meet current dam safety and environmental compliance standards in order to continue to provide a clean dependable water supply for the Upper Hood River valley. More information at: clearbranchdam.com.
MilestoneDate
NEPA Start Date 6/18/2025
Finding/Decision Date
📍 Mt. Hood National Forest 🏷 Special use management Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date 6/18/2025
Finding/Decision Date
Significant Effect
Significant Effect
Mt. Hood National Forest
MTH Lost Lake Late Successional Reserve Acre Swap
There is a need to amend the Forest Plan to remove the high use recreational area of Lost Lake Resort, Campground and Day Use Area from Late-successional Reserve (LSR), and reallocate more appropriate areas as LSR.
MilestoneDate
NEPA Start Date 8/20/2025
Finding/Decision Date
📍 Mt. Hood National Forest 🏷 Land management planning Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date 8/20/2025
Finding/Decision Date
Uncategorized
Uncategorized
Mt. Hood National Forest
MTH Timberline Chairlifts and Improvements
To improve connectivity between Summit Pass and Timberline Lodge, enhance skiing experience, and improve communications, the following is proposed: replacement of Summit Pass chairlift and new chairlift construction, ski terrain improvements, and fiber optic cable installation.
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Mt. Hood National Forest 🏷 Special use management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date
Finding/Decision Date
Uncategorized
Uncategorized
Inyo National Forest
Crystal Crag Water Storage Tank Replacement
The removal of two existing water storage tanks & constructing a new one. The new steel water storage tank will be 20,000-gallons, 16-foot diameter and 16 ft high. Including new inlet, outlet, drain, overflow, water supply, and distribution pipelines
MilestoneDate
Scoping Start 09/2024 (Estimated)
Decision 09/2024 (Estimated)
Implementation 09/2024 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
Scoping Start 09/2024 (Estimated)
Decision 09/2024 (Estimated)
Implementation 09/2024 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
E. Clampus Vitus Bodie Chapter No. 64 Tamarack Lodge Plaque
Bodie Chapter No. 64 of E. Clampus Vitus is to construct a historical marker w/ bronze plaque northeast of the Tamarack Lodge entrance commemorating the history of the Lodge & its contribution to the history of Mono County and the Mammoth Lakes Basin
MilestoneDate
Scoping Start 07/23/2024
Decision 08/2024 (Estimated)
Implementation 09/2024 (Estimated)
📍 Mammoth Ranger District 🏷 Heritage resource management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 07/23/2024
Decision 08/2024 (Estimated)
Implementation 09/2024 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
LADWP Long Valley Pole Removal and Pole Replacement Project
LADWP Utility Maintenance Project:1)removal of poles & replacement of poles in one line and 2)removal of poles & rehab in second line, 3)relinquish poles
MilestoneDate
Scoping Start 04/2024 (Estimated)
Decision 07/2024 (Estimated)
Implementation 10/2024 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
Scoping Start 04/2024 (Estimated)
Decision 07/2024 (Estimated)
Implementation 10/2024 (Estimated)
Significant Effect
Significant Effect
Inyo National Forest
Long Valley Exploration Drilling
On November 12, 2025, the Mammoth Lakes Ranger District of the Inyo National Forest received a Plan of Operations (Plan) from KORE USA Ltd. (KORE) for their Long Valley Exploration Drilling project in Mono County, California. KORE plans to conduct exploration-level activities for deposits of gold.
MilestoneDate
NEPA Start Date 4/3/2026
Finding/Decision Date
📍 Inyo National Forest 🏷 Minerals and geology Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date 4/3/2026
Finding/Decision Date
Uncategorized
Uncategorized
Inyo National Forest
Mammoth Mountain Main Lodge Redevelopment
Mammoth Mountain proposes redeveloping its Main Lodge area on private land, with related development on adjacent National Forest lands. Joint CEQA/NEPA analysis. Proposed construction/reconstruction of parking lots,buildings,chairlifts and ski runs.
MilestoneDate
NOI in Federal Register 11/14/2022
DEIS NOA in Federal Register 08/2025 (Estimated)
FEIS NOA in Federal Register 04/2025 (Estimated)
Objection Period Start 01/2026 (Estimated)
Decision 04/2026 (Estimated)
Implementation 04/2027 (Estimated)
📍 Inyo National Forest All Units 🏷 Recreation management · Special use management Added: 2026-05-28
In Progress
MilestoneDate
NOI in Federal Register 11/14/2022
DEIS NOA in Federal Register 08/2025 (Estimated)
FEIS NOA in Federal Register 04/2025 (Estimated)
Objection Period Start 01/2026 (Estimated)
Decision 04/2026 (Estimated)
Implementation 04/2027 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
Permit Reissuances - Ongoing, various permit types
Ongoing and continuous reissuance of various special use authorizations. Examples of these are resorts, research activities, utilities and events. For further information on any specific permit or permitted activities, contact Erin Noesser.
MilestoneDate
Scoping Start 12/10/2018
Decision 06/2026 (Estimated)
Implementation 06/2026 (Estimated)
📍 Inyo National Forest All Units 🏷 Special use management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 12/10/2018
Decision 06/2026 (Estimated)
Implementation 06/2026 (Estimated)
Restorative Impact
Restorative Impact
Inyo National Forest
Reds Meadow Valley Recreation Site Renovations
Renovations & ecological restoration at 7 recreation sites / campgrounds in Reds Meadow Valley designed to enhance overall visitor experience, ensure recreation assets support current & future visitation & protect/restore ecologically sensitive areas
MilestoneDate
Scoping Start 05/08/2024
Decision 12/2024 (Estimated)
Implementation 06/2025 (Estimated)
📍 Mammoth Ranger District 🏷 Recreation management · Watershed management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 05/08/2024
Decision 12/2024 (Estimated)
Implementation 06/2025 (Estimated)
Significant Effect
Significant Effect
Inyo National Forest
Rock Creek Lodge Resort Wildfire Resilience
Fuels reduction and forest resilience project surrounding the Rock Creek Lakes Resort permit area on the Inyo National Forest. Project is funded by a National Resources Conservation Service grant.
Learn About Wildfire Learn About Thinning
MilestoneDate
Scoping Start 09/01/2024
Decision 03/2025 (Estimated)
Implementation 06/2025 (Estimated)
📍 Inyo National Forest All Units 🏷 Fuels management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 09/01/2024
Decision 03/2025 (Estimated)
Implementation 06/2025 (Estimated)
Uncategorized
Uncategorized
Inyo National Forest
Sherwin Area Recreation Plan 3 (SHARP)
Development of designated trails for protection of natural and cultural resources. This proposed action includes decommissioning of user created trails, reconstruction of user created trails, and new trail construction.
MilestoneDate
Scoping Start 04/2025 (Estimated)
Decision 06/2025 (Estimated)
Implementation 07/2025 (Estimated)
📍 Mammoth Ranger District 🏷 Recreation management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
Scoping Start 04/2025 (Estimated)
Decision 06/2025 (Estimated)
Implementation 07/2025 (Estimated)
Significant Effect
Significant Effect
Los Padres National Forest
Establishing Interim Direction for Oil & Gas Leasing Management
Amend the Los Padres Forest Plan and the Southern California Forest Plan to establish interim direction for processing new lease applications for oil and gas, and remove references to and withdraw the 2005 Oil and Gas Record of Decision. https://usfs-public.box.com/s/8hb9zdav0fv3huge15oga4bzaec0yji6
MilestoneDate
NEPA Start Date 12/4/2025
Finding/Decision Date
📍 Los Padres National Forest 🏷 Land management planning Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date 12/4/2025
Finding/Decision Date
Uncategorized
Uncategorized
Los Padres National Forest
Los Prietos Helibase
The proposal is to construct a helicopter pad, associated safety facilities, and office space for the module within the lower compound at the Los Prietos Ranger Station.
MilestoneDate
NEPA Start Date 4/1/2026
Finding/Decision Date
📍 Santa Barbara Ranger District 🏷 Facility management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date 4/1/2026
Finding/Decision Date
Significant Effect
Significant Effect
Los Padres National Forest
Mount Pinos Forest Health Project - PALS #58380
Healthy Forest thinning project designed to improve the health and vigor of the existing stands and to make the stands more resilient to stressors such as drought, insects & wildfire.
Learn About Wildfire Learn About Thinning
MilestoneDate
NEPA Start Date 3/30/2021
Finding/Decision Date
📍 Los Padres National Forest 🏷 Forest products · Fuels management · Vegetation management (other than forest products) Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date 3/30/2021
Finding/Decision Date
Restorative Impact
Restorative Impact
Los Padres National Forest
Rose Valley Creek Restoration Project
This proposal aims to restore Rose Valley Creek to its historical stream function, form, and habitat to benefit native aquatic species and armor Rose Valley creek from future wildfires by bolstering the riparian zone.
MilestoneDate
Scoping Start 05/11/2022
Comment Period 06/09/2022
Decision 05/2025 (Estimated)
Implementation 08/2026 (Estimated)
📍 Ojai Ranger District 🏷 Wildlife, fish, rare plants · Watershed management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 05/11/2022
Comment Period 06/09/2022
Decision 05/2025 (Estimated)
Implementation 08/2026 (Estimated)