The LFDC NEPA Tracker monitors active NEPA projects across National Forests in Washington, Oregon, California, and Alaska, giving advocates real-time visibility into proposed logging, land management, and restoration activities on public lands.

Projects are updated daily and organized to quickly find new projects and ones currently inviting public participation.

This database contains only the projects that have been published by USFS and that are/were recently in the NEPA analysis page.
Recent policy changes at USFS and the increased use of Categorical Exclusions have drastically reduced the share of USFS projects that get published and/or invite public comment. This means many projects can only be discovered by the public through field monitoring, long after the project has been planned, approved, and contracted.
If your local forests are not yet being tracked, submit feedback using the link above to request the expanded coverage.

There is no 'alert' feature at this time, so check back regularly to learn about new projects and opportunity to comment.
Clear all
Show only: Significant Effect Mixed Impact Restorative Impact Uncategorized
Show only: Newly Added Taking Comments Now Show Inactive Projects
*Impact level assigned automatically, based on keywords and is intended as a general guide only
30 of 162 active projects
Mixed Impact
Mixed Impact
Taking Comments Now! 6/30/26 11:59 PM PDT
Los Padres National Forest
Wildfire Risk Reduction Project (formerly the Ecological Restoration Project) PALS # 62369
The project is designed to increase community/infrastructure protection, improve wildfire containment opportunities, and improve vegetation resilience to environmental stressors. A notice of Emergency Situation Determination approval has been posted. Comments will be accepted from June 24-30, 2026.
Learn About Wildfire Learn About Thinning
MilestoneDate
NEPA Start Date 7/29/2022
Finding/Decision Date
📍 Los Padres National Forest 🏷 Fuels management · Vegetation management (other than forest products) · Watershed management · Wildlife, fish, rare plants Added: 2026-05-28
3 Days Left to Comment
Taking Comments Now! 6/30/26 11:59 PM PDT
Developing Proposal
MilestoneDate
NEPA Start Date 7/29/2022
Finding/Decision Date
Significant Effect
Significant Effect
Mt. Hood National Forest
South Wasco Ecosystem Resiliency
The project proposes to conduct commercial and non-commercial fuels and vegetation treatments on approximately 19,000 acres.
Learn About Wildfire Learn About Thinning
Acres (approx.) 19,000
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Mt. Hood National Forest 🏷 Forest products · Fuels management · Regulations, directives, orders · Vegetation management (other than forest products) Added: 2026-06-15
Developing Proposal
Acres (approx.) 19,000
MilestoneDate
NEPA Start Date
Finding/Decision Date
Significant Effect
Significant Effect
Mt. Baker-Snoqualmie National Forest
2025 Mt. Baker Geothermal Consent to Lease
To explore or develop geothermal resources on National Forest lands, the USFS must consent to lease areas nominated by the BLM. This analysis does not authorize ground disturbance, but creates stipulations for authorized leasing areas. https://usfs-public.box.com/s/r56gzyn1msyfvj8md81arv1mo15tgoso
MilestoneDate
NEPA Start Date 9/10/2025
Finding/Decision Date
📍 Mt. Baker Ranger District 🏷 Minerals and geology Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date 9/10/2025
Finding/Decision Date
Uncategorized
Uncategorized
Mt. Baker-Snoqualmie National Forest
Deception Falls Trail Bridge Replacements
Replacement of 2 failing bridges with new bridges in more sustainable locations, with trail reroutes leading to the new locations. Bridges 70'-80' in length each, with about 750' of new trail total.
MilestoneDate
NEPA Start Date 1/15/2025
Finding/Decision Date 6/4/2026
📍 Skykomish Ranger District 🏷 Recreation management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
NEPA Start Date 1/15/2025
Finding/Decision Date 6/4/2026
Significant Effect
Significant Effect
Mt. Baker-Snoqualmie National Forest
Forestwide Thinning Analysis
This analysis will streamline the implementation of commercial thinning treatments designed to increase structural diversity of overstocked and planted stands and provide a sustainable flow of timber to local communities.
LFDC Commented Learn About Thinning
MilestoneDate
NEPA Start Date 9/3/2025
Finding/Decision Date
📍 Mt. Baker-Snoqualmie National Forest 🏷 Forest products Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date 9/3/2025
Finding/Decision Date
Mixed Impact
Mixed Impact
Mt. Baker-Snoqualmie National Forest
Martin Gap Restoration Thinning Project
This project aims to restore forest health and resilience, improve wildlife habitat, and support native plants that are important to Tribal communities by thinning and diversifying previously regenerated plantation stands.
Learn About Wildfire Learn About Thinning
Acres (approx.) 3,834
MilestoneDate
NEPA Start Date 9/1/2025
Finding/Decision Date
📍 Snoqualmie Ranger District 🏷 Vegetation management (other than forest products) · Wildlife, fish, rare plants Added: 2026-05-28
Developing Proposal Categorical Exclusion
Acres (approx.) 3,834
MilestoneDate
NEPA Start Date 9/1/2025
Finding/Decision Date
Uncategorized
Uncategorized
Mt. Baker-Snoqualmie National Forest
North Fork Stillaguamish Landscape Analysis
Landscape scale analysis of habitat restoration, and actions to improve ecological conditions.
MilestoneDate
NEPA Start Date 4/22/2022
Finding/Decision Date
📍 Mt. Baker-Snoqualmie National Forest Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date 4/22/2022
Finding/Decision Date
Mixed Impact
Mixed Impact
MBS, Okan-Wen, Colville, Wallowa-Whitman, Fremont-Winema, Deschutes, Umatilla, Malheur
Region 6 Elite Tree Protection Project
The Pacific Northwest Region is collaborating with nine Forests to develop a region-wide project to protect whitebark pine trees (Pinus albicaulis) that have a high level of white pine blister rust resistance.
Learn About Wildfire Learn About Thinning
MilestoneDate
Scoping Start 04/2023 (Estimated)
Decision 09/2023 (Estimated)
Implementation 09/2023 (Estimated)
📍 R6 - Pacific Northwest Region All Units 🏷 Wildlife, fish, rare plants · Vegetation management (other than forest products) Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
Scoping Start 04/2023 (Estimated)
Decision 09/2023 (Estimated)
Implementation 09/2023 (Estimated)
Mixed Impact
Mixed Impact
Mt. Baker-Snoqualmie National Forest
South Fork Canyon Creek Road Bridge Removal and Footbridge Install
Removal of the failed FSR 41 road bridge over the South Fork of Canyon Creek and removal of earth abutments in the creekbed to restore natural hydrologic flow. Construction of a footbridge for access to the area north of the creek for recreation use.
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Darrington Ranger District 🏷 Recreation management · Road management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date
Finding/Decision Date
Mixed Impact
Mixed Impact
Mt. Baker-Snoqualmie National Forest
Tenas Creek Restoration Project
The Darrington Ranger District proposes to replace a bridge on the Suiattle River Road to improve an important Chinook Salmon run and restore important salmon habitat for species.
MilestoneDate
NEPA Start Date 8/5/2022
Finding/Decision Date 4/16/2026
📍 Darrington Ranger District 🏷 Road management · Watershed management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
NEPA Start Date 8/5/2022
Finding/Decision Date 4/16/2026
Uncategorized
Uncategorized
Deschutes National Forest
2025 Crescent and Odell Lake Recreation Residence Small Projects Batch 1
Authorization was requested from 5 recreation residence owners on Crescent Lake, 4 owners on Odell Lake, and from the Shelter Cove Resort to complete minor upgrades or replacements such as deck or stair replacements and roof repairs.
MilestoneDate
Scoping Start 05/15/2025
Decision 09/2025 (Estimated)
Implementation 09/2025 (Estimated)
📍 Crescent Ranger District 🏷 Special use management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 05/15/2025
Decision 09/2025 (Estimated)
Implementation 09/2025 (Estimated)
Uncategorized
Uncategorized
Deschutes National Forest
Bend to Lava Lands Paved Path
Construct a non-motorized paved path that would provide connections to recreation sites south of Bend, OR. The entire length of the path would be from Baker Road to Lava Lands Visitor Center.
MilestoneDate
NEPA Start Date 3/3/2022
Finding/Decision Date
📍 Bend/Fort Rock Ranger District 🏷 Recreation management Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date 3/3/2022
Finding/Decision Date
Uncategorized
Uncategorized
Deschutes National Forest
Class 1, Pedal-assist E-bikes on Select Trails
This project is considering the use of class 1 e-bikes on select trails with the designed use of bicycle. The proposed action includes 67 trails, totaling 161.4 miles as open to class 1 e-bikes.
MilestoneDate
NEPA Start Date 7/2/2024
Finding/Decision Date
📍 Deschutes National Forest 🏷 Recreation management Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date 7/2/2024
Finding/Decision Date
Significant Effect
Significant Effect
Deschutes National Forest
Cougar Rock Restoration Project
The project proposes to maintain and restore resiliency and forest health and to address the potential risk of large-scale high severity wildfires. Proposed actions include thinning, mowing and prescribed burning on up to 2,800 acres.
Learn About Wildfire Learn About Thinning
Acres (approx.) 2,800
MilestoneDate
NEPA Start Date 12/16/2022
Finding/Decision Date
📍 Sisters Ranger District 🏷 Fuels management · Vegetation management (other than forest products) Added: 2026-05-28
Developing Proposal Categorical Exclusion
Acres (approx.) 2,800
MilestoneDate
NEPA Start Date 12/16/2022
Finding/Decision Date
Significant Effect
Significant Effect
Deschutes National Forest
Crate Vegetation Management Project and Site-Specific Forest Plan Amendment
Vegetation management on approximately 18,168 acres to move forest conditions toward historic range of variability and improve forest resilience to disturbance to reduce the likelihood of uncharacteristic large-scale loss of forest habitat.
Learn About Thinning
Acres (approx.) 18,168
MilestoneDate
NEPA Start Date 4/21/2026
Finding/Decision Date
📍 Bend/Fort Rock Ranger District 🏷 Forest products Added: 2026-05-28
Developing Proposal
Acres (approx.) 18,168
MilestoneDate
NEPA Start Date 4/21/2026
Finding/Decision Date
Significant Effect
Significant Effect
Deschutes National Forest
Flat Top Fire Site Preparation and Reforestation Project
This project proposes site preparation cutting and reforestation on approximately 9,530 acres that experienced a high basal area loss of vegetation as a result of the Flat Top Fire in 2024.
Learn About Wildfire Learn About Thinning
Acres (approx.) 9,530
MilestoneDate
Scoping Start 11/24/2025
Comment Period 12/08/2025
Decision 01/2026 (Estimated)
Implementation 03/2026 (Estimated)
📍 Deschutes National Forest All Units 🏷 Vegetation management (other than forest products) Added: 2026-05-28
In Progress Categorical Exclusion
Acres (approx.) 9,530
MilestoneDate
Scoping Start 11/24/2025
Comment Period 12/08/2025
Decision 01/2026 (Estimated)
Implementation 03/2026 (Estimated)
Significant Effect
Significant Effect
Deschutes National Forest
Green Ridge Landscape Restoration
The project would maintain and restore forest conditions closer to the historic range of variability and contribute to the restoration of ecosystem process and function in the planning area. Timber products are an outcome of restoration activities.
Learn About Wildfire Learn About Thinning
Acres (approx.) 25,000
MilestoneDate
NEPA Start Date 9/1/2017
Finding/Decision Date
📍 Sisters Ranger District 🏷 Forest products · Fuels management · Vegetation management (other than forest products) Added: 2026-05-28
Developing Proposal
Acres (approx.) 25,000
MilestoneDate
NEPA Start Date 9/1/2017
Finding/Decision Date
Significant Effect
Significant Effect
Deschutes National Forest
MODA Active Management Project
The MODA Active Management Project proposes dry forest restoration techniques in order to improve and maintain the forested ecosystem of of the Moore Creek and Davis Creek Subwatersheds on the Crescent Ranger District.
Learn About Wildfire Learn About Thinning
Acres 14,723
MilestoneDate
NEPA Start Date 3/2/2026
Finding/Decision Date
📍 Crescent Ranger District 🏷 Forest products · Vegetation management (other than forest products) Added: 2026-05-28
Developing Proposal
Acres 14,723
MilestoneDate
NEPA Start Date 3/2/2026
Finding/Decision Date
Uncategorized
Uncategorized
Deschutes National Forest
Sisters Trail Additions and Realignments (STAR)
The STAR project proposes several trail actions including new trail construction, additions of existing routes to the official Forest Service trail system, as well as realignments and decommissioning of existing trails on the Sisters Ranger District.
MilestoneDate
NEPA Start Date 7/23/2023
Finding/Decision Date
📍 Sisters Ranger District 🏷 Recreation management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date 7/23/2023
Finding/Decision Date
Mixed Impact
Mixed Impact
Deschutes National Forest
Upper Black Butte Swamp Restoration
Upper Black Butte Swamp is a 34-acre wetland that has incised channels and drying out vegetation. The project would restore the fen through channel filling, planting native vegetation, aspen restoration and invasive weed management.
Learn About Wildfire Learn About Thinning
MilestoneDate
NEPA Start Date 6/17/2025
Finding/Decision Date
📍 Sisters Ranger District 🏷 Vegetation management (other than forest products) · Watershed management · Wildlife, fish, rare plants Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date 6/17/2025
Finding/Decision Date
Uncategorized
Uncategorized
Deschutes National Forest
West Bend Trails Project
Trail modifications, such as reroutes, new trails, decommissioning to create a more sustainable trail network while minimizing resource impacts.
MilestoneDate
NEPA Start Date 2/29/2024
Finding/Decision Date
📍 Bend/Fort Rock Ranger District 🏷 Recreation management Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date 2/29/2024
Finding/Decision Date
Significant Effect
Significant Effect
Deschutes National Forest
West Bend Vegetation Management Project
Moving the area toward a more resilient landscape, providing a diversity of habitats, & reducing hazardous fuels. Approximately 14,750 acres of commercial thinning, for a total of 22,000 acres proposed for thinning, mowing, and/or underburning.
Learn About Wildfire Learn About Thinning
Acres of Thinning, Mowing, And/Or Underburning 22,000
Acres of Commercial Thinning 14,750
MilestoneDate
NEPA Start Date 11/24/2010
Finding/Decision Date
📍 Bend/Fort Rock Ranger District 🏷 Forest products · Fuels management · Vegetation management (other than forest products) Added: 2026-05-28
Developing Proposal
Acres of Thinning, Mowing, And/Or Underburning 22,000
Acres of Commercial Thinning 14,750
MilestoneDate
NEPA Start Date 11/24/2010
Finding/Decision Date
Significant Effect
Significant Effect
Mt. Hood National Forest
MTH Anvil Vegetation Management Project
This project seeks to improve forest health and diversity in plantations. In addition, this project seeks to reduce excessive fuel loading primarily along forest roads. Approximately 4,000 acres may be proposed for vegetation and fuels treatments.
Learn About Wildfire Learn About Thinning
Acres (approx.) 4,000
MilestoneDate
NEPA Start Date 2/3/2026
Finding/Decision Date
📍 Clackamas River Ranger District 🏷 Forest products · Fuels management · Vegetation management (other than forest products) Added: 2026-05-28
Developing Proposal
Acres (approx.) 4,000
MilestoneDate
NEPA Start Date 2/3/2026
Finding/Decision Date
Uncategorized
Uncategorized
Mt. Hood National Forest
MTH Clear Branch Dam Remediation
There is a need to remediate Clear Branch Dam to meet current dam safety and environmental compliance standards in order to continue to provide a clean dependable water supply for the Upper Hood River valley. More information at: clearbranchdam.com.
MilestoneDate
NEPA Start Date 6/18/2025
Finding/Decision Date
📍 Mt. Hood National Forest 🏷 Special use management Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date 6/18/2025
Finding/Decision Date
Significant Effect
Significant Effect
Mt. Hood National Forest
MTH Lost Lake Late Successional Reserve Acre Swap
There is a need to amend the Forest Plan to remove the high use recreational area of Lost Lake Resort, Campground and Day Use Area from Late-successional Reserve (LSR), and reallocate more appropriate areas as LSR.
MilestoneDate
NEPA Start Date 8/20/2025
Finding/Decision Date
📍 Mt. Hood National Forest 🏷 Land management planning Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date 8/20/2025
Finding/Decision Date
Uncategorized
Uncategorized
Mt. Hood National Forest
MTH Timberline Chairlifts and Improvements
To improve connectivity between Summit Pass and Timberline Lodge, enhance skiing experience, and improve communications, the following is proposed: replacement of Summit Pass chairlift and new chairlift construction, ski terrain improvements, and fiber optic cable installation.
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Mt. Hood National Forest 🏷 Special use management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date
Finding/Decision Date
Significant Effect
Significant Effect
Los Padres National Forest
Establishing Interim Direction for Oil & Gas Leasing Management
Amend the Los Padres Forest Plan and the Southern California Forest Plan to establish interim direction for processing new lease applications for oil and gas, and remove references to and withdraw the 2005 Oil and Gas Record of Decision. https://usfs-public.box.com/s/8hb9zdav0fv3huge15oga4bzaec0yji6
MilestoneDate
NEPA Start Date 12/4/2025
Finding/Decision Date
📍 Los Padres National Forest 🏷 Land management planning Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date 12/4/2025
Finding/Decision Date
Uncategorized
Uncategorized
Los Padres National Forest
Los Prietos Helibase
The proposal is to construct a helicopter pad, associated safety facilities, and office space for the module within the lower compound at the Los Prietos Ranger Station.
MilestoneDate
NEPA Start Date 4/1/2026
Finding/Decision Date
📍 Santa Barbara Ranger District 🏷 Facility management Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date 4/1/2026
Finding/Decision Date
Significant Effect
Significant Effect
Los Padres National Forest
Mount Pinos Forest Health Project - PALS #58380
Healthy Forest thinning project designed to improve the health and vigor of the existing stands and to make the stands more resilient to stressors such as drought, insects & wildfire.
Learn About Wildfire Learn About Thinning
MilestoneDate
NEPA Start Date 3/30/2021
Finding/Decision Date
📍 Los Padres National Forest 🏷 Forest products · Fuels management · Vegetation management (other than forest products) Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
NEPA Start Date 3/30/2021
Finding/Decision Date
Restorative Impact
Restorative Impact
Los Padres National Forest
Rose Valley Creek Restoration Project
This proposal aims to restore Rose Valley Creek to its historical stream function, form, and habitat to benefit native aquatic species and armor Rose Valley creek from future wildfires by bolstering the riparian zone.
MilestoneDate
Scoping Start 05/11/2022
Comment Period 06/09/2022
Decision 05/2025 (Estimated)
Implementation 08/2026 (Estimated)
📍 Ojai Ranger District 🏷 Wildlife, fish, rare plants · Watershed management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 05/11/2022
Comment Period 06/09/2022
Decision 05/2025 (Estimated)
Implementation 08/2026 (Estimated)