162 total Reset
The LFDC NEPA Tracker monitors active NEPA projects across National Forests in Washington, Oregon, California, and Alaska, giving advocates real-time visibility into proposed logging, land management, and restoration activities on public lands.

Projects are updated daily and organized to quickly find new projects and ones currently inviting public participation.

This database contains only the projects that have been published by USFS and that are/were recently in the NEPA analysis page.
Recent policy changes at USFS and the increased use of Categorical Exclusions have drastically reduced the share of USFS projects that get published and/or invite public comment. This means many projects can only be discovered by the public through field monitoring, long after the project has been planned, approved, and contracted.
If your local forests are not yet being tracked, submit feedback using the link above to request the expanded coverage.

There is no 'alert' feature at this time, so check back regularly to learn about new projects and opportunity to comment.
Clear all
Show only: Significant Effect Mixed Impact Restorative Impact Uncategorized
Show only: Newly Added Taking Comments Now Show Inactive Projects
*Impact level assigned automatically, based on keywords and is intended as a general guide only
Showing: Uncategorized · Mixed Impact
Mixed Impact
Mixed Impact
MBS, Okan-Wen, Colville, Wallowa-Whitman, Fremont-Winema, Deschutes, Umatilla, Malheur
Region 6 Elite Tree Protection Project
The Pacific Northwest Region is collaborating with nine Forests to develop a region-wide project to protect whitebark pine trees (Pinus albicaulis) that have a high level of white pine blister rust resistance.
Learn About Wildfire Learn About Thinning
MilestoneDate
Scoping Start 04/2023 (Estimated)
Decision 09/2023 (Estimated)
Implementation 09/2023 (Estimated)
📍 R6 - Pacific Northwest Region All Units 🏷 Wildlife, fish, rare plants · Vegetation management (other than forest products) Added: 2026-05-28
Developing Proposal Categorical Exclusion
MilestoneDate
Scoping Start 04/2023 (Estimated)
Decision 09/2023 (Estimated)
Implementation 09/2023 (Estimated)
Mixed Impact
Mixed Impact
Fremont-Winema National Forest
BPA-Lapine-Chiloquin Priority Pole Project
BPA has identified roads that require maintenance to ensure safe access to the LAPI-CHIL-1 transmission facilities. The road maintenance will allow BPA to also perform wood pole replacements that need to be completed along the transmission line.
MilestoneDate
Scoping Start 01/24/2023
Decision 06/2024 (Estimated)
Implementation 08/2024 (Estimated)
📍 Chemult Ranger District 🏷 Special use management · Road management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 01/24/2023
Decision 06/2024 (Estimated)
Implementation 08/2024 (Estimated)
Uncategorized
Uncategorized
Fremont-Winema National Forest
Buffalo Meadow Warming Shelter Project
This project proposes to install a pre-engineered shelter on the edge of a large meadow, known locally as Buffalo Meadow.
MilestoneDate
Scoping Start 01/18/2022
Decision 08/2026 (Estimated)
Implementation 11/2026 (Estimated)
📍 Klamath Ranger District 🏷 Special use management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 01/18/2022
Decision 08/2026 (Estimated)
Implementation 11/2026 (Estimated)
Uncategorized
Uncategorized
Fremont-Winema National Forest
Chiloquin Sewer project
This project will connect the Chiloquin Ranger District to the town of Chiloquin's sewer line
MilestoneDate
Scoping Start 03/20/2015
Decision 01/1970 (Estimated)
Implementation 06/2015 (Estimated)
📍 Chiloquin Ranger District 🏷 Facility management Added: 2026-05-28
In Progress Categorical Exclusion
MilestoneDate
Scoping Start 03/20/2015
Decision 01/1970 (Estimated)
Implementation 06/2015 (Estimated)
Uncategorized
Uncategorized
Fremont-Winema National Forest
Mt. McLoughlin Trailhead Relocation Project
There is a need to relocate the Mt. Mcloughlin Trailhead and parking area to avoid initial and long-term maintenance costs associated with constructing a new bridge across the Cascade Canal.
MilestoneDate
Scoping Start 11/2024 (Estimated)
Comment Period 02/2025 (Estimated)
Objection Period Start 05/2025 (Estimated)
Decision 09/2025 (Estimated)
Implementation 06/2026 (Estimated)
📍 Klamath Ranger District 🏷 Recreation management Added: 2026-05-28
Developing Proposal
MilestoneDate
Scoping Start 11/2024 (Estimated)
Comment Period 02/2025 (Estimated)
Objection Period Start 05/2025 (Estimated)
Decision 09/2025 (Estimated)
Implementation 06/2026 (Estimated)