415 total Reset
The LFDC NEPA Tracker monitors active NEPA projects across National Forests in Washington, Oregon, California, and Alaska, giving advocates real-time visibility into proposed logging, land management, and restoration activities on public lands.

Projects are updated daily and organized to quickly find new projects and ones currently inviting public participation.

This database contains only the projects that have been published by USFS and that are/were recently in the NEPA analysis page.
Recent policy changes at USFS and the increased use of Categorical Exclusions have drastically reduced the share of USFS projects that get published and/or invite public comment. This means many projects can only be discovered by the public through field monitoring, long after the project has been planned, approved, and contracted.
If your local forests are not yet being tracked, submit feedback using the link above to request the expanded coverage.

There is no 'alert' feature at this time, so check back regularly to learn about new projects and opportunity to comment.
Clear all
Show only: Significant Effect Mixed Impact Restorative Impact Uncategorized
Show only: Newly Added Taking Comments Now Show Inactive Projects
*Impact level assigned automatically, based on keywords and is intended as a general guide only
Showing: Significant Effect
Significant Effect
Significant Effect
Klamath National Forest
Discovery Day Mine
The Discovery Day Mins is an established mine site that consists of a road, three working pads, and underground tunnels. A Plan of Operations has been proposed to mine the Discovery Day claim
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Salmon River Ranger District 🏷 Minerals and geology Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date
Finding/Decision Date
Significant Effect
Significant Effect
Klamath National Forest
Goosenest Developed Recreation Sites Fuels Reduction Project
Remove hazardous fuels from within and around all developed recreation sites on the Goosenest Ranger District.
Learn About Wildfire Learn About Thinning
📍 Klamath National Forest All Units 🏷 Recreation management · Fuels management Added: 2026-05-28
Completed
Significant Effect
Significant Effect
Klamath National Forest
Klamath and Shasta-Trinity National Forests' Prescribed Fire Project
Fuels reduction and prescribed fire across the landscape. Project details: https://www.fs.usda.gov/r05/klamath/projects/66583
Learn About Wildfire Learn About Thinning
MilestoneDate
NEPA Start Date 12/19/2025
Finding/Decision Date
📍 Klamath National Forest 🏷 Fuels management Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date 12/19/2025
Finding/Decision Date
Significant Effect
Significant Effect
Klamath National Forest
McKinney Fire Restoration EA_Veg/Fuels
The McKinney Fire Restoration EA is proposed within and adjacent to the 2022 McKinney Fire footprint with the purpose of increasing wildfire resilience on the landscape. Proposed activities include a variety of fuels reduction treatments.
Learn About Wildfire Learn About Thinning
MilestoneDate
NEPA Start Date
Finding/Decision Date
📍 Oak Knoll Ranger District 🏷 Fuels management · Vegetation management (other than forest products) Added: 2026-05-28
Developing Proposal
MilestoneDate
NEPA Start Date
Finding/Decision Date
Significant Effect
Significant Effect
Klamath National Forest
Seiad Restoration Thin
The project will treat 3,350 acres within the 4,648-acre project boundary for fire risk reduction and community and resource protection within the Wildland Urban Interface.
Learn About Wildfire Learn About Thinning
Acres 3,350
MilestoneDate
NEPA Start Date 1/23/2026
Finding/Decision Date
📍 Klamath National Forest 🏷 Forest products · Fuels management Added: 2026-05-28
Developing Proposal
Acres 3,350
MilestoneDate
NEPA Start Date 1/23/2026
Finding/Decision Date
Significant Effect
Significant Effect
Klamath National Forest
South Fork
The South Fork project is an active management project with the purpose of addressing hazardous fuels conditions along roads and private property, as well as aligning with Executive Order 14225, Immediate Expansion of American Timber Production.
Learn About Wildfire Learn About Thinning
MilestoneDate
Scoping Start 06/2026 (Estimated)
Comment Period 09/2026 (Estimated)
Decision 11/2026 (Estimated)
Implementation 04/2027 (Estimated)
📍 Klamath National Forest All Units 🏷 Forest products · Fuels management Added: 2026-05-28
Developing Proposal
MilestoneDate
Scoping Start 06/2026 (Estimated)
Comment Period 09/2026 (Estimated)
Decision 11/2026 (Estimated)
Implementation 04/2027 (Estimated)
Significant Effect
Significant Effect
Klamath National Forest
Tennant Waterline
This project proposes to replace approximately two miles of water pipeline and two water troughs in the Bray cattle allotment on the Goosenest Ranger District.
📍 Goosenest Ranger District 🏷 Grazing management Added: 2026-05-28
Completed